Overview

Project Overview

UDOT is running a project to renew approximately four miles of SR-13 and SR-83 through Corinne (see map below) by placing an asphalt surface treatment called a Bonded Wearing Course (BWC). A BWC is used to extend the life of the existing pavement, while also restoring skid resistance and sealing the road surface to improve drainage. This project also includes removing and replacing pedestrian ramps to bring them up to current ADA standards, replacing barrier, and updating road signs, lighting, striping, and rumble strips.
 

Project Map

PIN 20886 | Road construction map of the project taking place on SR-13 through Corinne, from I-15 to the Walmart Distribution Center
 

Project Timeline

  • Construction began on June 15, 2026, and is expected to reach completion by mid-August 2026.

Schedule

Work Hours: 7 p.m. to 7 a.m.

Workdays: Nightly from Sunday night - Friday morning (weekend night work may take place on occasion if needed)

Minor construction activities will take place during the day, but these items will not impede traffic.

*Schedules are subject to change due to weather conditions and material availability.

Project Timeline

live
live

June - August 2026 - Construction

complete
complete

Project Milestones

  • Construction began on June 15, 2026.
  • Concrete work was completed on June 24, 2026.

Contact Information

To contact the public information team with questions or concerns:

Hotline: 877-495-4240

Email: sr13renewed@utah.gov

Stay Informed

To receive weekly construction updates, please contact the public information team at the email address above and enter "Updates" in the subject line.