Andover - 159th Street East
Andover - 159th Street East
Project: 159th Street East, from US-54/400 to Central Ave in Andover
Scope: Improve the existing two-lane road with ditches to three-lane urban curb and gutter with adjacent 10' bicycle/pedestrian path from the intersection of US-54/400 to Central Avenue.
Total Cost: $6.6 million
WAMPO Funding Request: $4.485 million
Project Background: Over the past several years, the area has transitioned from rural to suburban, and this arterial road serving the neighborhood needs to be upgraded to suburban standards and increased capacity.