Briar Creek Gwy Phase 1

Briar Creek Gwy Phases 1-3

Briar Creek Gwy Phase 1

July 17, 2026 Update: 

NEW: the artist designing the public art component of the project, Jim Gallucci, will be leading a community engagement conversation and walk on site, hosted by the Arts & Science Council (ASC), on Thursday, August 27th from 6-7pm. The flyer is forthcoming; but please hold the date if interested.

Unexpected soils and rock issues with the pilings for the greenway bridge across Briar Creek between the Monroe Road/Bramlet Road trailhead parking lot and the main trail continue to hamper construction on this phase of the project. Additional structural engineering design was completed and four of the five required pilings have been embedded; but the final piling has proven difficult to set, and additional review is needed prior to further construction. However, the design and construction team continues actively moving the project forward toward completion as soon as possible.

Most of the asphalt trail has been completed between the Bay Street junction and the playground area of Chantilly Park; please note that this is an active construction project site and not yet open for use.

North bridge piling construction: 

Bridge Piling Construction 1

Bridge Piling Construction 2

 

Greenway trail closure signage at Laburnam Avenue:

Laburnam Ave. Trailhead Closure Signage

 

View of the paved greenway between Laburnam and Bay through Chantilly Park and Ecological Sanctuary:

Briar Creek Gwy Phase 1 between Wyanoke and Bay

 

Did you know a small coffee shop will be adjacent to the trailhead parking lot? It's under construction now:

Future Coffee Shop at Monroe/Bramlet

 

June 11, 2026 Update: The greenway trailhead parking lot at the Monroe Road/Bramlet Road intersection has now been paved, along with some of the trailhead greenway itself (see photos below). An update to the design of the northern bridge abutment is under review. Please be reminded that it's an active construction project site and not yet open for use by the public.

Briar Creek Gwy Ph 1 parking lot paving

 

Briar Creek Gwy Ph 1 greenway trailhead paving

June 2, 2026 Update: Although much of the Phase 1 main line greenway has now been paved (see photos below), please be reminded that it's an active construction project site and not yet open for use by the public. The trailhead parking lot on Bramlet Rd. is expected to be paved the week of June 8th. And although the bridge has been placed on the construction site we have run into difficulty with the bridge's pilings. Our engineers are working on options and we hope to resolve this issue as quickly as possible so the bridge can be set over the  creek.

 

Briar Creek Greenway Phase 1

 

Briar Creek Greenway Phase 1 Paving

 

Briar Creek Greenway Phase 1 - Parking Lot Fine Grading

 

Briar Creek Greenway Phase 1 trailhead parking lot - fine grading

 

Briar Creek Greenway Phase 1 Bridge To Be Installed

 

 

September 16, 2025 Construction Photos:

Early Trailhead Parking Lot Construction:

Bramlet Road parking lot

 

Bramlet Rd. Bridge Demolition:

Bramlet bridge demolition

 

 

Please provide us with any comments or questions you may have about the project.

Would you like to provide your contact information for future project updates?

Greenway Master Plan:

Map of the Mecklenburg County Greenway Master Plan

If you have any questions regarding this project, please contact:

George Berger, Senior Planner

George.Berger@mecklenburgcountync.gov or 980-214-7248

OR

Katie Lloyd, Senior Planner

Katie.Lloyd@mecklenburgcountync.gov or 980-266-0691