Transportation Improvement Program (TIP) Amendments- December 2021
Transportation Improvement Program (TIP) Amendments- December 2021
GTC Planning Committee recommended the following amendments for Board consideration. Comments can be submitted through the day prior to the meeting to be included in the public record. For more information contact Alex Kone by email or calling 585-232-6240 extension 212.
TIP Amendments to be considered at December 9, 2021 meeting of the GTC Board
Proposed TIP Amendments
Proposed Council Resolution 21-90 (Amending the 2020-2024 TIP by adding the FFY 2022 Railway-Highway Crossing (Section 130) projects)
Rt 78/98 – Arcade and Attica Railroad, Town of Java
(TIP # H20-63-WY2, PIN 493419) – NYSDOT
Add a New Project with a Total Cost of $389,550 ($389,550 Federal);
Add a FFY 2022 Detailed Design phase of $32,550 ($32,550 Federal);
Add a FFY 2023 Construction phase of $357,000 ($357,000 Federal).
The source of Federal funds is the Railway-Highway Crossings (Section 130), managed by NYSDOT Main Office. The Federal Share in excess of 90% is provided via Toll Credits earned by NYS.
Rt 262 (Townline Rd) – CSX Transportation, Town of Bergen
(TIP # H20-64-GN2, PIN 493420) – NYSDOT
Add a New Project with a Total Cost of $615,825 ($615,825 Federal);
Add a FFY 2022 Detailed Design phase of $56,700 ($56,700 Federal);
Add a FFY 2023 Construction phase of $559,125 ($559,125 Federal).
The source of Federal funds is the Railway-Highway Crossings (Section 130), managed by NYSDOT Main Office. The Federal Share in excess of 90% is provided via Toll Credits earned by NYS.
Rt 63 (Ellicott St) – Depew, Lancaster, & Western Railroad, City of Batavia
(TIP # H20-65-GN2, PIN 493421) – NYSDOT
Add a New Project with a Total Cost of $68,775 ($68,775 Federal);
Add a FFY 2022 Detailed Design phase of $3,675 ($3,675 Federal);
Add a FFY 2023 Construction phase of $65,100 ($65,100 Federal).
The source of Federal funds is the Railway-Highway Crossings (Section 130), managed by NYSDOT Main Office. The Federal Share in excess of 90% is provided via Toll Credits earned by NYS.
Lynch Rd – Falls Road Railroad, Town of Murray
(TIP # H20-66-OR2, PIN 493422) – NYSDOT
Add a New Project with a Total Cost of $258,825 ($68,775 Federal);
Add a FFY 2022 Detailed Design phase of $6,825 ($6,825 Federal);
Add a FFY 2023 Construction phase of $252,000 ($252,000 Federal).
The source of Federal funds is the Railway-Highway Crossings (Section 130), managed by NYSDOT Main Office. The Federal Share in excess of 90% is provided via Toll Credits earned by NYS.
Lake Ave (CR 120) – Ontario Midland Railroad, Town of Williamson
(TIP # H20-67-WA2, PIN 493423) – NYSDOT
Add a New Project with a Total Cost of $451,500 ($451,500 Federal);
Add a FFY 2022 Detailed Design phase of $36,750 ($36,750 Federal);
Add a FFY 2023 Construction phase of $414,750 ($414,750 Federal).
The source of Federal funds is the Railway-Highway Crossings (Section 130), managed by NYSDOT Main Office. The Federal Share in excess of 90% is provided via Toll Credits earned by NYS.
Wilson Rd (CR 261) – Ontario Midland Railroad, Town of Butler
(TIP # H20-68-WA2, PIN 493424) – NYSDOT
Add a New Project with a Total Cost of $115,500 ($115,500 Federal);
Add a FFY 2022 Detailed Design phase of $10,500 ($10,500 Federal);
Add a FFY 2023 Construction phase of $105,000 ($105,000 Federal).
The source of Federal funds is the Railway-Highway Crossings (Section 130), managed by NYSDOT Main Office. The Federal Share in excess of 90% is provided via Toll Credits earned by NYS.