General Services: CityLYNX Gold Line UpdatesHeader with GL logo
Rendering of Johnson & Wales stop (looking west)

CityLYNX Gold Line Phase 2

Update for June 19, 2020

 

Project Progress

Some aspects of the project have been affected by COVID-19. Staff is working with the contractor to determine the extent of impact on the project schedule.

In response to the recent protests, the contractor has had to clear construction materials and debris from worksites each day to ensure the safety of protestors and police officers. Staff is working with the contractor to determine the potential impact of these events on the project schedule.

End-of-line trackwork has been installed at French Street on the western end of the alignment. The project team is awaiting a final quality control release from the trackwork manufacturer in order for work to continue. Preparation of the ground for end-of-line trackwork at Sunnyside Avenue is complete and awaiting the installation of the trackwork. The trackwork manufacturer must be on-site to perform a quality control evaluation during the setting of the trackwork at Sunnyside Avenue. Due to COVID-19, the scheduling of the out-of-town manufacturer's representative has been rescheduled for later this month.

The contractor continues median, planting strip and other related roadway work in the Uptown area.

Most of the poles for the overhead wiring system have been installed, with 20% more remaining at various locations along the alignment.

Construction on the Hawthorne Lane bridge continues. Concrete work, including medians, sidewalks, approach slabs and bridge sides, will continue through July.

Six vehicles and seven substations are in various stages of testing.

 

Project Schedule (Major Milestones)

JUNE 2020 Overall project •	Schedule manufacturer quality control evaluation so special trackwork installation can continue at French Street and Sunnyside Avenue •	Continue roadway work throughout project area •	Continue installation of overhead wire system foundations and poles and begin overhead wire installation •	Continue punch list items (roadway, curb, track, sidewalk and fencing)	Hawthorne Lane Bridge •	Pour approach slab on Sunnyside Avenue side •	Pour concrete medians and sidewalks (potential early morning work) •	Cure concrete JULY – AUGUST 2020 Overall project •	Continue special trackwork installation at French Street and Sunnyside Avenue •	Continue roadway work throughout project area •	Continue overhead wire installation •	Complete trackwork installation •	Continue punch list items	Hawthorne Lane Bridge •	Complete concrete pours for bridge sides (potential early morning work) and install railings •	Pour concrete medians and sidewalks •	Cure concrete •	Install track on bridge (early morning work) •	Install roadway pavement markings •	Bridge opens to the public SEPTEMBER – LATE 2020/EARLY 2021 •	Complete overhead wire installation •	Complete platform shelters and amenities •	Complete roadway work throughout project area •	Conduct in-street vehicle testing •	Continue punch list items  STREETCAR BEGINS PASSENGER SERVICE

Regular construction hours typically are 7 a.m. to 7 p.m. Crews may be onsite preparing work before 7 a.m. Concrete pours will be during the night or in the early morning due to temperature restrictions.

We understand the overnight concrete work will affect the community. We will provide notification 48 hours in advance of night or early-morning work whenever possible. The dates for the work may change due to inclement weather; however, an updated notice will be sent. Please be aware that 48 hours' notice cannot be given for emergencies that require immediate attention. City staff will notify individuals directly if access to their driveway is affected by construction.

City inspectors will be at various locations checking quality control and adherence to project plans.

 

Road and Lane Closures

CURRENT FUTURE

Montgomery Street between Trade Street and Frazier Avenue - northbound lanes closed (through June 22, 2020)

West Trade Street at Wesley Heights Way - partial street closure (through June 23, 3030)

Tryon Street between 4th & 5th Streets - reduced to one lane each direction with lane shifts (extended through July 17, 2020)

Beatties Ford Road between French Street and Dixon Street, including the intersection at Beatties Ford Road and Mill Street (extended through July 24, 2020)

Hawthorne Lane and Sunnyside Avenue - lanes closed both directions (extended through July 29, 2020)

Hawthorne Lane between Sunnyside Avenue and Bay Street - Use East 7th and Central Avenue as detour (through August 8, 2020)

There are no future street closures scheduled at this time                               

For details and detours on road and lane closures affected by the CityLYNX Gold Project, please visit Charlotte Department of Transportation's interactive street closure page and visit the Gold Line Phase 2 project web page.

Weather and unforeseen circumstances occasionally prevent work from being completed as scheduled and make it unsafe to reopen lanes or streets as planned. When this occurs, City staff and contractors work to resolve the situation as quickly as possible and reduce impacts to the traveling public.

Pedestrians should stay out of work zones. Those walking near work zones should be alert, cautious and allow extra traveling time. It is advised they cross at signalized intersections, use pedestrian signals where available and abide by detour signage.

Motorists traveling through work zones should be alert and extra cautious. Drivers should get in the correct lane well in advance and constantly be on the lookout for vehicles merging into adjacent travel lanes as they approach a work zone. Drivers should double their following distances.

Questions? Please contact Tim Morton, Chief Construction Inspector, at 704-361-5735 or temorton@charlottenc.gov.


Sent on behalf of City of Charlotte, NC
600 East 4th Street, Charlotte, NC 28202
 
Unsubscribe | My Subscriptions | Support
 
View this email in a browser