We are committed to keeping you informed as progress is made on the CityLYNX Gold Line Phase 2 Project. This includes information we receive from the contractor, which, due to the nature of construction, changes frequently.
The Hawthorne Lane bridge concrete deck pour for Thursday, May 14 has been postponed to Friday, May 15. If weather impedes, this work will take place on Saturday, May 16. Crews will be onsite by 2 a.m. in order to prepare for the pour, which will start between 3 a.m. and 4 a.m.
This will be the first of three major concrete pours. Pending inspections and tests, the second pour may be May 18 or 19, and the third pour may be May 22 or 23.
Expect heavy machinery noise (i.e. engines, concrete trucks backing up, concrete pumping trucks) and light towers illuminating the site.
This schedule could change based on weather and other factors. We will notify you if the pour is rescheduled.
Please contact Tim Morton at temorton@charlottenc.gov if you have any questions.
|