Oak Knoll Flood Risk Reduction

November 2, 2026 | Walnut Creek | CIP ID: 5789.102

We’re sharing a quick update on current and upcoming work.

 

Columbia Oaks Drive

Work continues in the Columbia Oaks Drive area.

Completed work: 

  • Installed three rows of concrete box culverts between J Gregg Cove and Columbia Oaks Court.
  • Installed one row of box culverts in J Gregg Cove. 

Current and upcoming work: 

  • Installation of concrete box culverts between J Gregg Cove and Jollyville Road. Similar to work already completed, we will first install the two rows of concrete box culverts closest to the office building. Traffic will then shift so the third row can be installed. Flaggers will direct traffic during the day and yield signs are in place overnight. Please use caution while entering or exiting Columbia Oaks Drive.  

  • After this is complete, we will finish installing the storm drain system near Columbia Oaks Court. 

  • Major construction in this area is expected to be complete by the end of the calendar year. The road will have a temporary asphalt surface until final restoration of the street and sidewalk towards the end of the project.

 

Woodcrest Drive

Water and wastewater relocation along Woodcrest Drive was scheduled to begin from the public utility easement and moving towards the Chelsea Moor Pond. However, we are working to resolve underground utility conflicts on Woodcrest Drive between the public utility easement and Three Oaks Trail. Water, wastewater, and storm drain lines share limited space beneath the road and there are specific requirements regarding spacing. 

Once work begins, progress will be slow since we will be digging through rock. It is expected to take three months to complete the segment between the public utility easement and Three Oaks Trail. During construction, the road will either be reduced to one lane with flaggers directing traffic or a detour will be in place when full road closure is required. 

Please expect noise and dust in the area. We will use jackhammers and other equipment to break through the limestone rock so we can install the concrete box culvert. This is a slow and noisy process, so we appreciate your patience while this work is in progress.

 

Water and Wastewater

We will need to shut off water periodically to complete some of the work for this project. 

We will leave a notice on the front door of affected homes 48 hours in advance with two exceptions: 

  • We may briefly turn off water without notice to test valves and equipment ahead of a planned outage. 

  • There is always the possibility of a temporary, loss of water or other service if a pipe or line is broken. We’ll respond immediately to restore service if this happens. We have done extensive research ahead of time to pinpoint where all the underground utilities are. This should avoid unplanned outages. 

If your residence is to be affected by a planned outage, please consider storing water in a pitcher or bathtub in order to have water supplies on hand during the shutoff. When services are restored, please flush your lines by running a cold-water bathtub spigot and an outside faucet for 10-15 minutes before using other faucets. This rids the system of any natural sediment buildup that may have occurred over the years. It’s helpful to rinse out faucet screens as well. 

Austin Water Dispatch is available 24/7 at 512-972-1000 for any water-related issues.

 

Work Reminders

  • Work hours are Monday-Sunday 7 a.m. to 7 p.m. 

  • Construction hours adhere to the City’s Noise Ordinance. 

  • Slow down near construction, stay alert, and follow all posted signs. 

  • Please note that as with any construction project, schedules are projected as accurately as possible and are subject to change due to the nature of construction and weather.

 

Stay Connected

Help us keep everyone informed by sharing this email with your neighbors and visiting family and friends. If someone shared this with you and you want to be included on future emails, signup for project updates. 

There is more information on the project web page. You may also reach out to one of the project team members: 

  • Timmie Bui, Project Manager, Austin Capital Delivery Services, 512-974-7199 

  • Matt Miller, Project Inspector, Austin Capital Delivery Services, 832-863-2004 

Thank you for your patience as we work to reduce flood risk in your neighborhood