A completed section of the shared-use path near the Airport Boulevard and Koenig Lane intersection, enhancing safety and accessibility for pedestrians and cyclists.
Construction on the Airport Boulevard corridor from 45th Street to 55th Street continues to make progress.
Completed: We have successfully installed 692 feet of shared-use path from Middle Fiskville Road to 55th Street.
In Progress: Crews are currently working on the section from 51st Street to 46th Street.
At this time, the project is approximately 20% complete and remains on schedule for full completion by the end of May 2025. Please note, these dates are subject to change.
These improvements are part of our ongoing efforts to enhance safety, accessibility, and connectivity along Airport Boulevard. We appreciate your continued patience and cooperation as we work toward completing these enhancements for all corridor users.
|