SR-201 | 900 W to State Street Paving
CONSTRUCTION UPDATE
June 13, 2025
We appreciate your patience as we kicked off the SR-201 2100 S paving project last week. Over the next few weeks, crews will be upgrading pedestrian ramps to meet ADA compliance at intersections from 900 W to State Street. There will also be various locations within the travel lanes where crews will be lowering utility covers in preparation for paving activity. We want to remind motorists traveling through the area at night to stay clear of construction zones separated by barrels and cones. These traffic control devices are in place to safely guide drivers into open lanes. Please follow all posted traffic signage. Thank you for your continued patience and for staying informed about this project.
|
|
|
|
Upgraded pedestrian ramp at 2100 S and 900 W Intersection | 06-13-25

Pedestrian ramp ADA upgrades at 2100 S and 300 W Intersection | 06-13-25
|
|
|
|
SCHEDULE
Work Hours: 7pm - 6am; Occasional Days 6am - 10am
Workdays: Mon - Sat (No Holidays)
Project Total Duration: Approximately 75 days
Schedules are subject to change due to weather conditions and material availability.
|
|
|
|
CONSTRUCTION ACTIVITES & TRAFFIC IMPACTS
- Starting June 4: Crews begin upgrading pedestrian ramps.
- June 16 - June 28: Crews will begin lowering utilities.
- Work will require rolling single lane closures at night.
- Starting June 29: Paving Operations begin. Full nighttime single-lane closures in both directions are expected.
- Sunday Night, June 29: I-15 NB and SB On-ramps from 2100 S closed. Detours will be posted.
|
|
|
|
|
|
|
PROJECT DESCRIPTION
The Utah Department of Transportation (UDOT) will resurface State Route 201 (2100 S) from 900 W to State Street. The project objectives are aimed at preserving the life of the road. This paving process will help increase the longevity of the road surface, address road imperfections and enhance motorist safety by providing a smoother, more durable road. Additional work includes upgraded pedestrian ramps to meet ADA compliance and refreshed lane painting/striping. See our project website for more details.
| Know before you go. Check UDOT Traffic before hitting the road |
UDOT has established a project-dedicated public involvement team for the SR-201 Paving Project.
|
|
|
|
SAFETY NOTICE:
For your safety and the safety of those working in the area, please use extra caution, reduce speeds, and follow all posted signs and signals when driving through construction zones. Barrels and other traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.
|
|
|
|
|
|
|
|
|