I-80 | Parleys Canyon Upgrade
CONSTRUCTION UPDATE
June 11, 2025

We are grateful to our crews for the timely completion of drainage enhancements on the eastbound lanes. As part of ongoing improvements along I-80, crews will be performing paving operations over the next couple of weeks. This will require nighttime ramp and lane closures in the project area in both directions (Exits 132 - 134. See construction impacts for more details on ramp closures). Detours will be in place, and short delays are possible, especially during peak travel times. Please plan ahead and use extra caution when driving through the work zone. In addition, motorists using the on- and off-ramps during the day may encounter minor surface bumps where paving is underway. These will be brief but noticeable, so please drive with care. We appreciate your patience as paving operations on I-80 begin!

 

 

SCHEDULE

 

 

Work Hours: Mostly Nighttime (7pm - 6am); Some Daytime work as necessary
Workdays: Tuesday Night - Sunday Night

Project Total Duration:  Approximately 75 days

Schedules are subject to change due to weather conditions and material availability.

 

 

CONSTRUCTION ACTIVITES & TRAFFIC IMPACTS

 

  • Wednesday June 11th - Saturday June 14th
    • Eastbound Ramp closures from Exit 132 - 134 as paving operations begin. Detours are posted using an alternate route of Lambs Canyon (Exit 137) and head westbound to reach desired off-ramp.

 

  • Starting as early as Monday June 16th - Wednesday June 18th
    • Paving operations will begin on westbound ramps. Nighttime ramps closures possible from Exit 132 - Exit 134. Detours posted using an alternate routeof Exit 131 and head eastbound to reach desired off-ramp.

 

  • Starting as early as Wednesday June 18th
    • ​​​​​​​Paving operations begin on mainline eastbound travel lanes and then will move to westbound, which will both require night lane closures using barrels to guide vehicles into open lanes to safely complete the work. Motorists can expect short travel delays during peak travel periods.  We encourage planning ahead and using caution when traveling through the construction zones.

 

 

 


 

PROJECT DESCRIPTION

The Utah Department of Transportation (UDOT) will resurface I-80, from Lower Parleys Canyon to SR-65 (exit 134). The project objectives are aimed at preserving the life of the road. This paving process will not only help increase the longevity of the road but also address roadway structural integrity and enhance motorist safety by providing a smoother, more durable road surface.  The on/off ramps along the route will also be resurfaced. Additional work includes variable drainage enhancements, barrier upgrades, and updated roadside signage and road surface striping.

Know before you go. Check UDOT Traffic before hitting the road

 

UDOT has established a project-dedicated public involvement team for the I-80 Mouth of Parleys Paving Project.

 

For More Project Information:

Hotline:  801-838-8362

Email: i80parleyspaving@utah.gov

Project Website: udotinput.utah.gov/i80parleyspaving

 

SAFETY NOTICE:

For your safety and the safety of those working in the area, please use extra caution, reduce speeds, and follow all posted signs and signals when driving through construction zones. Barrels and other traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.