Work In Progress
- Demolition Areas:
- Men’s and Women’s Shower & Dressing
- Rotunda
- Beverly Sheffield Education Center - Splash! Exhibit Area
- Asbestos abatement and lead-based paint remediation
- Salvage of structural glazed tile units to make repairs at interior sides of masonry walls
Planned Work
- Installation of new water and wastewater lines within the building
- Installation of new electrical lines within the building
- Installation of new fiber line
- Installation of concrete foundation
Figure 1 - New West Side Pool Entrance near shower and restroom trailers
Figure 2 - New sidewalk at West Side Pool Entrance near showers and restrooms
Figure 3 - Rotunda Demolition
Figure 4 - Splash! Exhibit Demolition
Please continue to check back for project updates and photos of the progress. For more information on the overall project, including frequently asked questions, please visit the Joan Means Khabele Bathhouse at Barton Springs Pool Rehabilitation project page here.
Please note that as in any construction project, schedules are projected as accurately as possible, and all dates are subject to change due to the nature of construction and weather.
Reminder:
During the Bathhouse Rehabilitation project, Barton Springs Pool will maintain its regular schedule and remain open to swimmers. However, William Barton Drive, leading to the parking lot adjacent to the Bathhouse, will be closed to general public parking and drop-offs during construction. Parking in the other lots at Zilker Park will remain open, with wayfinding signage guiding pedestrians to the north side pool entrance. Pedestrian access routes through the construction site will be adjusted as work progresses. Public ADA-accessible parking and emergency vehicle access will be available throughout the construction period. The south side pool entry gate and parking lot at Azie Morton will remain unchanged throughout this time.
Please note that parking fees at Zilker Park have started on holidays and weekends.
Avoid the traffic and ride the Zilker Shuttle!
The Zilker Shuttle runs from 12:00 p.m. to 8:30 p.m. every Saturday and Sunday, in addition to Memorial Day and Labor Day. Please note, the shuttle hours for the Fourth of July holiday are from 12:00 to 5 p.m. This is the third summer the Department has offered a free off-site parking option and shuttle to Zilker Park. The program's new route utilizes two CapMetro bus stops on Barton Springs Road and adds a pick-up from the Stratford gravel parking lot. For more information please visit www.austintexas.gov/zilker.
Bathhouse Renamed
On April 4, 2024, an Austin City Council resolution renamed the Bathhouse at Barton Springs Pool in honor of Joan Means Khabele for her contributions and activism which led to the integration of the pool.
To learn more about Joan Means Khabele, please visit the Parks and Recreation Department’s blogpost here.
For more information on the renaming of the bathhouse, please visit the Barton Springs Bathhouse Renaming Proposal webpage here.
Stay informed on the rehabilitation project on the project webpage here.
Questions or concerns should be directed to:
Paul Mendoza, AIA, Project Manager
Capital Delivery Services
Paul.Mendoza@austintexas.gov
512-974-1272
Ellen Colfax, RA, Project Manager
Parks and Recreation Department
Ellen.Colfax@austintexas.gov
512-974-9472