Brassiewood Dr. Phase 2  South Pleasant Valley Rd. Outfall

November 9, 2026| Williamson Creek | CIP ID: 5789.144

 

We’re sharing a quick update on our progress so far.  

Work at the outfall:  

Last month, we installed measures to prevent erosion and protect water quality during construction at the existing drainage outfall where Pleasant Valley Road crosses over Williamson Creek. We also prepared the area for construction of the concrete support piers. Over the past couple of weeks, we’ve continued work on the piers and have a couple more remaining to install. Over the next few weeks, we’ll finish the foundation work, continue building the walls and outfall, and install supports for a nearby utility pole. 

Work at the detention pond:  

At the detention pond, we demolished and removed the existing weir structure. Work continues on the headwall, the concrete structure that helps direct stormwater flow, at the existing detention pond.  

Traffic 

We’ve heard from the community that the traffic along South Pleasant Valley Road is frustrating due to all the construction. There are two projects happening around the intersection of William Cannon and South Pleasant Valley Road.  

One of the projects is this one, Phase 2 of the Brassiewood Flood Risk Reduction project happening in your neighborhood. We are coordinating with the other project and have adjusted the traffic control plan  to help improve traffic flow through the construction area. Flow through our area appears to have improved. 

We are also taking the steps below to permanently improve our portion (which stops at Williamson Creek) as follows: 

  •  The project team updated the construction plan to reduce traffic changes throughout the project.  

  • Most of the work will be completed under a single traffic setup, reducing the need for lane shifts and other traffic changes during construction.  

  • At least one neighborhood entrance from South Pleasant Valley Road, either at Creek Bend Drive or Brassiewood Drive, will remain open at all times.  

  • The updated plan gives crews more room to work and is expected to shorten construction by several weeks. 

Traffic relating to this project will be affected at least through next May. 

The second project will improve safety for everyone traveling through the intersection. Crews are currently working on the northwest corner of South Pleasant Valley Road and William Cannon Drive to build the new right-turn lane. This work is expected to continue for another two to three weeks.  

Once the right-turn lane is complete, crews will install a shared-use path along the west side of South Pleasant Valley Road north of William Cannon Drive, ending near the bridge. 

Crews will then move to the southwest corner of the intersection. This phase will require a temporary detour for some vehicles. The final phase of work will take place on the southeast corner of the intersection. 

We will continue to keep you updated on any changes to traffic control plans in addition to other project updates.  

Work Reminders 

  • Work hours are Monday-Sunday 7 a.m. to 7 p.m.  

  • Construction hours adhere to the City’s Noise Ordinance.  

  • Slow down near construction, stay alert, and follow all posted signs.  

  • Please note that as with any construction project, schedules are projected as accurately as possible and are subject to change due to the nature of construction and weather. 

Stay Connected 

Help us keep everyone informed by sharing this email with your neighbors and visiting family and friends. If someone shared this with you and you want to be included on future emails, signup for project updates.  

There is more information on the project web page.  

You may also reach out to one of the project team members listed below.  

Key Contacts

  • Craig.McColloch@austintexas.gov, Project Manager, 512-749-3412  

  • Blair.Mancini@austintexas.gov, Construction Coordinator, 737-701-7634  

  • Heather.Peart@austintexas.gov, Project Sponsor, 737-393-6106 