Beverly S. Sheffield Northwest Pool Project

Tot Pool with zero depth entrance and shade structure posts

Tot pool with zero depth entrance and shade structure posts

 

November Update

 

Construction and renovations began in January 2025 and is anticipated to be complete for swim season 2026. During construction, the pool, bathhouse, and a portion of the surrounding parking lot will be closed to the public. The tennis and basketball courts, playground, and pond will remain accessible through the park road. For more information on the history of the project, please visit our webpage at Beverly S. Sheffield Northwest Aquatic Facility Renovation | AustinTexas.gov 

October Progress

Recent work includes:

  • New zero entrance at tot pool
  • Pool decks
  • Entrance plaza and stairs
  • Electric and plumbing work
  • Myrtha pool panels
  • Bathhouse walls for family restroom
  • Pool lights
  • Historic bathhouse tile repairs
  • Rock planter wall
  • Plaza trench drains
  • Shade structure post footings and posts
  • Entrance ramp railing
  • Water taps
Early morning Installation of the perimeter pool deck

Early morning installation of the perimeter pool deck

 

Upcoming Work

•    Irrigation 
•    Entrance gate
•    Myrtha pool liner 
•    Bathhouse plumbing fixtures 
•    Terrazzo divider repairs
•    Toilet stall partitions 
•    Painting 
•    Light fixture 
•    Landscaping 
•    Benches and bike rack 
•    Shade structure fabric

Past newsletters on the overall project can be found on the project webpage here.

Diving board on new pool deck

Diving board on new pool deck

Shade structure posts shown being installed with a crane.

Shade structure posts installation

 

Scheduled Milestones

•    Construction began January 2025 
•    Anticipated completion of all major construction activity is spring of 2026 for a pool opening during the swim season of 2026.


Please note that as in any construction project, schedules are projected as accurately as possible. All dates are subject to change due to the nature of construction and the weather. 
 

 

Project Team

Project Management – JMT International
Architect/Engineering – Marmon Mok
Construction Manager at Risk – Flintco Construction
Parks and Recreation Department: Project Manager – D’Anne Williams


 

Other Park Projects Update

 

Playscape Replacement

Austin Parks and Recreation has begun gathering information working towards replacement of the existing playscape just south of the pool. The department will set up community meetings once a timeline for the project has been determined.


Shoal Creek Dam Modernization


Austin Watershed Protection Department continues to work on the design for the dam improvements and anticipates submitting for permit review in early 2026. More information on this project can be found at Creek Flooding | AustinTexas.gov 


Park Pond

The water level at the Beverly S. Sheffield Northwest District Park Duck Pond has dropped over the summer after a long-standing underground leak near the pool was repaired, which had been an unrecognized source of water for the pond. Austin Parks and Recreation is taking short-term steps to protect trees and wildlife including watering trees within the boundaries of the constraints of water conservation code. For the long term, APR is collaborating with Austin Watershed Protection to evaluate sustainable, long-term solutions for the pond. More information will be shared with the community once more work has been done to study the options. 
 