[ SEE PROJECT WEBSITE ]

State Street | North Temple to 400 S Paving
CONSTRUCTION UPDATE
June 6, 2025

We appreciate your patience as we kicked off the State Street paving project earlier this week. Over the next few weeks, crews will be upgrading pedestrian ramps to meet ADA compliance at intersections from North Temple to 400 S. There will also be various locations within the travel lanes where crews will be lowering utility covers in preparation for paving activity. Due to the nature of this work, residents may experience moderate noise as crews use demolition equipment to complete these tasks. We apologize for any inconvenience this may cause. We also want to remind motorists traveling through the area at night to stay clear of construction zones separated by barrels and cones. These traffic control devices are in place to safely guide drivers into open lanes. Please follow all posted traffic signage including detour routes. Thank you for your continued patience and for staying informed about this project.

 

 

SCHEDULE

 

 

Work Hours: Night Work (7pm - 6am)
Workdays: Sunday Night - Friday Morning

Project Total Duration:  Approximately 75 days

Schedules are subject to change due to weather conditions and material availability.

 

 

CONSTRUCTION ACTIVITES & TRAFFIC IMPACTS

 

June 2 - 27: Pedestrian ramp upgrades at intersections. Lowering of several dozen utility covers.

 

Starting as early as the week of June 30th: Nighttime paving operations begin. Dates TBA as the work approaches.

 

 


 

PROJECT DESCRIPTION

The Utah Department of Transportation (UDOT) will resurface State Street (SR-186) from North Temple to 400 S in Salt Lake County. The project objectives are aimed at preserving the life of the road. This paving process will help increase the longevity of the road surface, address road imperfections and enhance motorist safety by providing a smoother, more durable road. Additional work includes upgraded pedestrian ramps to meet ADA compliance, refreshed lane painting/striping. See our project website for more details.

Know before you go. Check UDOT Traffic before hitting the road

 

UDOT has established a project-dedicated public involvement team for the State Street; North Temple to 400 S Paving Project.

 

For More Project Information:

Hotline:  801-838-8362

Email: statestreetpaving@utah.gov

Project Website: udotinput.utah.gov/statestreetpaving

 

SAFETY NOTICE:

For your safety and the safety of those working in the area, please use extra caution, reduce speeds, and follow all posted signs and signals when driving through construction zones. Barrels and other traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.

 

 

Sent on behalf of Utah DOT by PublicInput.com
To subscribe, please send an email to statestreetpaving@utah.gov with "Updates" in the subject line
 
Unsubscribe | My Subscriptions
 