November 2024
Emma S. Barrientos Mexican American Cultural Center Phase 2 Improvements Project Update
Please see the information below for the latest updates on progress, photos, and announcements:
- Exterior circulation corridors for the second floor are being waterproofed.
- Foundation footings for the Zocalo are being coordinated with stormwater pipe locations and tree roots to avoid conflicts.
- Electrical transformers have been delivered to the building for installation.
- Welding inspections were completed prior to continuing erection of the shade structure.
- An opening was carefully cut in the existing precast concrete panels to connect the old and the new building addition.
- Roofing has begun with installation of the metal decking and with parapet blocking for the roof edge secured in place.
- A brick mock-up reflecting architectural coursing detail has been prepared for the team to review.
- Paint mock-up of a steel column was prepared illustrating the finish option for the team to review.
North Building Addition: Exterior corridor being waterproofed on second floor.
Zocalo: Excavation for stormwater lines.
Zocalo: Shade structure welding in progress.
North Building Addition: Metal roof decking and parapet blocking.
Mock-up: Painted steel for review and inspection.
Mock-up: Textured brick installation for review and inspection.
SCHEDULED MILESTONES
- Construction began – August 28, 2023
- Anticipated completion of all major construction activity – Summer 2025
- Anticipated grand opening – Fall 2025
Please note that as with any construction project, schedules are projected as accurately as possible, and all dates are subject to change due to the nature of construction and weather.
This is an active construction site. For the safety of the public, unauthorized entry is not permitted.
For information on MACC programs and staff relocations during construction, visit the MACC webpage. For project updates, visit the project website.
Project Manager: Heidi Tse
512-974-7172
Heidi.Tse@AustinTexas.gov
Project Inspector: Mark Burton
512-974-7117
Mark.Burton@AustinTexas.gov
PARD Liaison : George Maldonado
512-974-9525
George.Maldonado@AustinTexas.gov
|