Emma S. Barrientos Mexican American Cultural Center Phase 2 Improvements Project Update

 

Please see the information below for the latest updates on progress, photos, and announcements:

  • Exterior circulation corridors for the second floor are being waterproofed.
  • Foundation footings for the Zocalo are being coordinated with stormwater pipe locations and tree roots to avoid conflicts.
  • Electrical transformers have been delivered to the building for installation.
  • Welding inspections were completed prior to continuing erection of the shade structure.
  • An opening was carefully cut in the existing precast concrete panels to connect the old and the new building addition.
  • Roofing has begun with installation of the metal decking and with parapet blocking for the roof edge secured in place.
  • A brick mock-up reflecting architectural coursing detail has been prepared for the team to review. 
  • Paint mock-up of a steel column was prepared illustrating the finish option for the team to review.  

Exterior corridor being waterproofed on second floor.

North Building Addition: Exterior corridor being waterproofed on second floor.

 

Zocalo: Excavation for stormwater lines.

Zocalo: Excavation for stormwater lines.

 

Zocalo: Shade structure welding in progress.

Zocalo: Shade structure welding in progress.

 

North Building Addition: Metal roof decking and parapet blocking.

North Building Addition: Metal roof decking and parapet blocking.

 

Mock-up: Painted steel for review and inspection.

Mock-up: Painted steel for review and inspection.

 

Mock-up: Textured brick installation for review and inspection.

Mock-up: Textured brick installation for review and inspection.

 

ANNOUNCEMENTS

  • City Council has approved artists Katherine Telley and Ruben Esquivel to design and fabricate artwork for the EST MACC Phase 2, Art in Public Places (AIPP) Project. A kick-off meeting has been scheduled for later this month. More announcements regarding the planned community engagement for this project can be found at the AIPP website here.
  • Concrete pours and steel deliveries will continue. Work hours will adhere to the City’s noise ordinance. Ordinance information can be found here.
  • The Confluence, a separate public/private partnership project, has delivered the lattice bridge on-site this month. The parking lot remains as the construction access point. Temporary trail detours and additional project information can be found here.
  • Read last month's project update here.

 

SCHEDULED MILESTONES

  • Construction began – August 28, 2023
  • Anticipated completion of all major construction activity – Summer 2025
  • Anticipated grand opening – Fall 2025

 

Please note that as with any construction project, schedules are projected as accurately as possible, and all dates are subject to change due to the nature of construction and weather.

 

This is an active construction site. For the safety of the public, unauthorized entry is not permitted.

 

For information on MACC programs and staff relocations during construction, visit the MACC webpage. For project updates, visit the project website.

 

Project Manager: Heidi Tse

512-974-7172

Heidi.Tse@AustinTexas.gov

 

Project Inspector: Mark Burton

512-974-7117

Mark.Burton@AustinTexas.gov

 

PARD Liaison : George Maldonado

512-974-9525

George.Maldonado@AustinTexas.gov

For more information, email CapitalDelivery@AustinTexas.gov

Visit us online at AustinTexas.gov/Emma-S-Barrientos-Mexican-American-Cultural-Center

Share this news on social media
    
Capital Delivery Services logo 300 dpi
Unsubscribe | My Subscriptions
View this email in a browser