I-80 | Parleys Canyon Upgrade
CONSTRUCTION UPDATE
July 10, 2025

We’re cruising right along with the I-80 Parleys Canyon Paving Project and want to keep you in the loop! Over the past few weeks—excluding the holiday—our crews have been hard at work repaving the main travel lanes which will continue through July 16. Up next: lane striping and rumble strip installation—which means two-lane closures will stick around a bit longer. We've also noticed peak traffic tends to hit between 8:30 and 10:30pm, so if you're able to travel outside those hours, it may help you avoid delays.

Looking ahead, we’re on track to wrap up by end of July. And good news—UDOT’s other I-80 project near Kimball Junction is on pause until July 16 to help ease congestion.

Huge thanks to our crews and to you for your patience as we smooth the way forward!

 

New Pavement on Outside Lanes | I-80 Exit 133 Looking East | 07/10/25

 

 

SCHEDULE

 

 

Work Hours: Mostly Nighttime (7pm - 6am); Some Daytime work as necessary
Workdays: Monday Night - Saturday Morning; Sunday night only as necessary

Project Total Duration:  Approximately 75 days

Schedules are subject to change due to weather conditions and material availability.

 

 

CONSTRUCTION ACTIVITIES & TRAFFIC IMPACTS

 

  • Thursday, July 10 - Wednesday, July 16
    • Paving Operations continue and will require nighttime closures of two lanes in both eastbound and westbound directions starting as early as 7pm.
    • Barrels and cones will be used to safely guide vehicles into the open lanes during this work. 
  • Thursday, July 17 - Wednesday July 30
    • Road striping and rumble strip operations will require closures of two lanes in both eastbound and westbound directions
  • End of July:
    • Project will be substantially complete.

 

 


 

PROJECT DESCRIPTION

The Utah Department of Transportation (UDOT) will resurface I-80, from Lower Parleys Canyon to SR-65 (exit 134). The project objectives are aimed at preserving the life of the road. This paving process will not only help increase the longevity of the road but also address roadway structural integrity and enhance motorist safety by providing a smoother, more durable road surface.  The on/off ramps along the route will also be resurfaced. Additional work includes variable drainage enhancements, barrier upgrades, and updated roadside signage and road surface striping.

Know before you go. Check UDOT Traffic before hitting the road

 

UDOT has established a project-dedicated public involvement team for the I-80 Mouth of Parleys Paving Project.

 

For More Project Information:

Hotline:  801-838-8362

Email: i80parleyspaving@utah.gov

Project Website: udotinput.utah.gov/i80parleyspaving

 

SAFETY NOTICE:

For your safety and the safety of those working in the area, please use extra caution, reduce speeds, and follow all posted signs and signals when driving through construction zones. Barrels and other traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.

 

Sent on behalf of Utah DOT by PublicInput.com