Translate this email
Chinese (Simplified) / 简体中文 | French / Français | German / Deutsch | Haitian Creole / Kreyòl Ayisyen | Hindi / हिन्दी | Japanese / 日本語 | Myanmar (Burmese) / မြန်မာစာ | Portuguese (Portugal, Brazil) / Português | Russian / Русский | Spanish / Español

July 2024

Emma S. Barrientos Mexican American Cultural Center Phase 2 Improvements Project Update

 

Please see the information below for the latest updates on progress, photos, and announcements.

  • Foundation piers for the circular shade structure at the zocalo or plaza are in progress.
  • The new elevator pit has been formed and poured. Demolition of old elevator is underway.
  • The below ground south stairs and building addition foundation system are complete.
  • The mechanical room in the Central Utility Plant (CUP) is being made ready for final connections to the Austin Energy (AE) Chilled Water District Cooling Network. Project engineers are ensuring that equipment is in proper working order and compliant with AE requirements.
  • The stucco wall finish on the Central Utility Plant has been installed.
  • Level one concrete slab pours are planned for July.
  • Structural steel erection is planned for this month and marks the beginning of vertical construction.

Zocalo: One of four foundation piers for the shade structure.

 

South Building Addition: New elevator pit.

 

North Building Addition: Below ground foundation completed.

 

Central Utility Plant (CUP): Stucco wall finish application while in progress.

 

ANNOUNCEMENTS

 

  • Concrete pours are planned for July, steel delivery is expected in August. Work hours will adhere to the City’s noise ordinance. Ordinance information can be found here.  
  • The Confluence, a separate public/private partnership project to stabilize and protect the ecology of Waller Creek, improve water quality, and create a continuous hike and bike trail along the creek is expected to increase activities at the MACC, as the parking lot is the construction access point for the east side of the creek delta. Weekend activity is planned for June 2024. Additional information can be found here.
  • Read last month's project update here.

 

SCHEDULED MILESTONES

 

  • Construction began – August 28, 2023
  • Anticipated completion of all major construction activity – Summer 2025
  • Anticipated grand opening – Fall 2025

 

Please note that as in any construction project, schedules are projected as accurately as possible, and all dates are subject to change due to the nature of construction and weather.

 

This is an active construction site. For the safety of the public, unauthorized entry is not permitted.

 

For information on MACC programs and staff relocations during construction, visit the MACC webpage. For project updates, visit the project website.

 

Project Manager: Heidi Tse

512.974.7172

Heidi.Tse@AustinTexas.gov

 

Project Inspector: Mark Burton

512.974.7117

Mark.Burton@AustinTexas.gov

 

PARD Liaison : George Maldonado

512.974.9525

George.Maldonado@AustinTexas.gov

For more information, email CapitalDelivery@AustinTexas.gov

Visit us online at AustinTexas.gov/Emma-S-Barrientos-Mexican-American-Cultural-Center

Share this news on social media
    
Capital Delivery Services logo 300 dpi
Unsubscribe | My Subscriptions
View this email in a browser