Richmond Tributary Rehabilitation Project

November 17, 2026 | Williamson Creek | CIP ID: 5848.041

Dear Residents,  

We are reaching out to provide an update on the Richmond Tributary Channel Rehabilitation Project. This project will stabilize the eroding channel bank, improve culverts, and upgrade water and wastewater pipes. 

Work relocating utility lines and removing poles in the channel has started and will continue into December. This work is necessary to prepare the channel and ensure there is enough space for construction. Due to the upcoming holiday season, there will not be traffic or road impacts for this project in November and December. 

The remaining work for this project is expected to occur in six phases. Please be aware that this phasing plan and durations are subject to change, and we will update you as adjustments are made. As each phase approaches, we will provide more details on road closures and detours and will coordinate with affected residents. Please see the image below for a map of these phases. 

Phase 1:

  • Channel improvements from Redd St to Philco Dr
  • Approximate duration: January to Fall 2027

Phase 2: 

  • Wastewater line relocation on Gillis St 
  • Approximate duration: Summer to Fall 2027

Phase 3:

  • Channel improvements from Philco Dr to Green Forest Dr
  • Water line improvements at Philco Dr
  • Approximate duration: Fall 2027 to Summer 2028

Phase 4:

  • Wastewater line upgrades on Richmond Ave
  • Approximate duration: Fall 2027 to early 2028

Phase 5:

  • Channel improvements, culvert replacement, and water and wastewater line improvements at Green Forest Dr
  • Approximate duration:  2028

Phase 6:

  • Final asphalt repaving for roads in all phases
  • Approximate duration:  2028
Map of Richmond Tributary Rehabilitation Project phases

Key Contacts

  • Ria Yamaguchi, Project Manager, Ria.Yamaguchi@austintexas.gov, (512) 974-9125 

  • Helen Hartman, Project Sponsor, helen.hartman@austintexas.gov, (737)-359-5448. 

  • Quintin Leday, Project Inspector, Quintin.Leday@austintexas.gov, (512) 809-7870 

  • For more information on the project, please visit austintexas.gov/watershed-protection/projects/erosion-projects 

  • If you were forwarded this email, you can sign up for email updates at publicinput.com/richmond 

City of Austin
Sent on behalf of City of Austin, TX by PublicInput
2409 Crabtree Blvd, Suite 107, Raleigh, NC 27604
 
Unsubscribe | My Subscriptions
 
View this email in a browser | 🌍 Translate