Dear Residents,
We are reaching out to provide an update on the Richmond Tributary Channel Rehabilitation Project. This project will stabilize the eroding channel bank, improve culverts, and upgrade water and wastewater pipes.
Work relocating utility lines and removing poles in the channel has started and will continue into December. This work is necessary to prepare the channel and ensure there is enough space for construction. Due to the upcoming holiday season, there will not be traffic or road impacts for this project in November and December.
The remaining work for this project is expected to occur in six phases. Please be aware that this phasing plan and durations are subject to change, and we will update you as adjustments are made. As each phase approaches, we will provide more details on road closures and detours and will coordinate with affected residents. Please see the image below for a map of these phases.
Phase 1:
- Channel improvements from Redd St to Philco Dr
- Approximate duration: January to Fall 2027
Phase 2:
- Wastewater line relocation on Gillis St
- Approximate duration: Summer to Fall 2027
Phase 3:
- Channel improvements from Philco Dr to Green Forest Dr
- Water line improvements at Philco Dr
- Approximate duration: Fall 2027 to Summer 2028
Phase 4:
- Wastewater line upgrades on Richmond Ave
- Approximate duration: Fall 2027 to early 2028
Phase 5:
- Channel improvements, culvert replacement, and water and wastewater line improvements at Green Forest Dr
- Approximate duration: 2028
Phase 6:
- Final asphalt repaving for roads in all phases
- Approximate duration: 2028
|