August 2024

Emma S. Barrientos Mexican American Cultural Center Phase 2 Improvements Project Update

 

Please see the information below for the latest updates on progress, photos, and announcements.

  • The foundation slabs were poured for both the north and south building additions. 
  • The new air conditioning system is expected to connect to Austin Energy Chilled Water District Cooling Network and to operate this month.
  • Framing for the new ceilings, or soffits, at the exterior walkways is being constructed.
  • Grease trap for teaching kitchen is in place and connected below ground.
  • Structural steel erection will start this month with the south building addition followed by the north addition.

 

South Building Addition: Foundation slab.

 

North Building Addition: Foundation slab.

 

South Building Addition: Grease trap for the Teaching Kitchen.

 

 

 

ANNOUNCEMENTS

 

  • Concrete pours will continue.  Steel and the construction crane delivery are expected this month.  Work hours will adhere to the City’s noise ordinance. Ordinance information can be found here.  
  • The Confluence, a separate public/private partnership project, has increased activities at the MACC, as the parking lot is the construction access point. Additional information can be found  here.
  • Read last month's project update here.

 

SCHEDULED MILESTONES

 

  • Construction began – August 28, 2023
  • Anticipated completion of all major construction activity – Summer 2025
  • Anticipated grand opening – Fall 2025

 

Please note that as in any construction project, schedules are projected as accurately as possible, and all dates are subject to change due to the nature of construction and weather.

 

This is an active construction site. For the safety of the public, unauthorized entry is not permitted.

 

For information on MACC programs and staff relocations during construction, visit the MACC webpage. For project updates, visit the project website.

 

Project Manager: Heidi Tse

512.974.7172

Heidi.Tse@AustinTexas.gov

 

Project Inspector: Mark Burton

512.974.7117

Mark.Burton@AustinTexas.gov

 

PARD Liaison : George Maldonado

512.974.9525

George.Maldonado@AustinTexas.gov

For more information, email CapitalDelivery@AustinTexas.gov

Visit us online at AustinTexas.gov/Emma-S-Barrientos-Mexican-American-Cultural-Center

Share this news on social media
    
Capital Delivery Services logo 300 dpi
Unsubscribe | My Subscriptions
View this email in a browser