Construction Beginning on New Wishbone Bridge at Longhorn Dam!
Construction on the Longhorn Dam Multimodal Improvements Project will begin Monday, July 1.
Please see our project timeline below for the latest information!
July 1 - Construction Begins
- Trail users will notice fencing being installed around the planned construction areas of Canterbury Park, Longhorn Shores and Krieg Fields.
- The public will still have full access to Krieg Fields during construction.
- Longhorn Shores will be closed to the public.
- The tunnel from Krieg Fields under Pleasant Valley Road will be closed to the public.
- Mulch sock and erosion control measures will be put into place in designated construction areas.
July 8 - Closures Begin
- Vehicular traffic going eastbound on Canterbury Street will be closed. One way traffic flow will continue westbound.
- Access to Canterbury Park and its parking lot will be closed to the public.
- The unnamed peninsula beginning near Holly Street will be closed to the public.
July 15 - Hike and Bike Trail Detour Begins
- Users of the Ann and Roy Butler Hike and Bike Trail will be rerouted northbound along the east side of Pleasant Valley Road.
- The detour will continue westbound along Canterbury Street and complete southbound down Pedernales and Holly Streets.
- The detour is expected to last for 18 months.
The timeline for construction is dependent on weather conditions. We appreciate your patience and cooperation as we begin this project to enhance connectivity on the Ann and Roy Butler Hike and Bike Trail.
|