Carter Ann Patton Stormwater Improvement Project Update May 8, 2025

We want to provide you with an update on traffic control and paving work in the area of Patton Avenue. 

Due to changes in the asphalt plant availability during nighttime hours, the night closures will need to be rescheduled. We will notify you as soon as new dates are confirmed.

Additionally, please note that lane closures on N French Broad Avenue will now begin next week, starting the week of May 12. Once work at the SE corner of French Broad Ave is complete, crews will move to the NE corner of the same intersection. See map below. 

 

Thank you for your attention to these updates. Please feel free to reach out with any questions, and we will continue to keep you informed as the schedule is finalized.

Nicole Peterson 

Project Manager

City of Asheville, Public Works - Stormwater 

npeterson@ashevillenc.gov

Sent on behalf of City of Asheville, NC by PublicInput
2409 Crabtree Blvd, Suite 107, Raleigh, NC 27604
Unsubscribe | My Subscriptions
View this email in a browser | 🌍 Translate