SR-201 | 900 W to State Street Paving
CONSTRUCTION UPDATE
July 31, 2025

We’re excited to share that the paving project on State Route 201 (2100 South) is nearing completion. A big thank you to our crews for helping everything run smoothly. This coming week, crews will finish up a few final tasks, which will require rolling single-lane closures. This paving project is expected to be substantially complete by August 7. We appreciate your patience as we’ve worked to enhance the road for everyone’s benefit.

Please note that additional construction will continue along 2100 South near the Central Pointe Station as crews upgrade the railroad crossing. This work will take place during nighttime hours (7 p.m. to 6 a.m.) and will involve intermittent single-lane and shoulder closures. These upgrades are expected to continue through early September. Thank you again for your continued understanding as we work to improve the road!

 

New pavement and Lane Striping | 400 W 2100 S | 07/28/25

 

 

SCHEDULE

 

 

Work Hours: 7pm - 6am
Workdays: Mon - Sat; Railroad construction Sunday PM - Friday AM

Project Total Duration:  Approximately 75 days

Schedules are subject to change due to weather conditions and material availability.

 

 

CONSTRUCTION ACTIVITIES & TRAFFIC IMPACTS

 

 

  • 7/28 - 8/7: Crews will be continuing raising utilities and other various activities in order to finish the project. This will require rolling single-lane closures throughout the project area.

    • Paving project will be substantially complete by 8/7

 

  • 7/28: 2100 South railway construction (near Central Pointe Station) begins and will continue for approximately 50 days.

    • Motorists can expect various single-lane and shoulder closures at night while work is taking place

 

 


 

 

PROJECT DESCRIPTION

The Utah Department of Transportation (UDOT) will resurface State Route 201 (2100 S) from 900 W to State Street. The project objectives are aimed at preserving the life of the road. This paving process will help increase the longevity of the road surface, address road imperfections and enhance motorist safety by providing a smoother, more durable road. Additional work includes upgraded pedestrian ramps to meet ADA compliance and refreshed lane painting/striping. See our project website for more details.

Know before you go. Check UDOT Traffic before hitting the road

 

UDOT has established a project-dedicated public involvement team for the SR-201 Paving Project.

 

For More Project Information:

Hotline:  801-838-8362

Email: sr201paving@utah.gov

Project Website: udotinput.utah.gov/sr201paving

 

SAFETY NOTICE:

For your safety and the safety of those working in the area, please use extra caution, reduce speeds, and follow all posted signs and signals when driving through construction zones. Barrels and other traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.

 