[ SEE PROJECT WEBSITE ]

 

SR-162/262 SAn Juan County Paving Logo

State Route 162 & 262 | San Juan County Improved | Energy Corridor
April 27, 2026

 

IMPROVING TRAVEL AT MONTEZUMA CREEK

 

Just one month ago, the SR-162/SR-262 intersection operated under stop control, requiring drivers to slow, wait, and take turns to proceed. Since the roundabout opened, traffic is moving more efficiently through the area, reducing delays and improving overall operations.

This new configuration is designed to enhance safety and mobility by lowering vehicle speeds, improving visibility, and providing clearer navigation with updated signage and roadway features. These improvements help streamline traffic movements while maintaining consistent flow through the intersection.

Early operations indicate the roundabout is functioning as intended, providing a more efficient and reliable experience for daily travel through the corridor. We thank the public for their patience during construction and the transition to the new traffic pattern.

New roundabout and signs at SR-162/262

SR-162/262 | Montezuma Creek Roundabout and Signage | 04/15/26

 

KEY MILESTONES ACHIEVED

 

We are happy to report that several key elements of the project are now finished! Improvements along SR-262 between US-191 and Montezuma Creek are fully complete, and all guardrail installation and roadside signage across the corridor have been finalized. These upgrades enhance both safety and overall driving conditions. We are grateful to our crews for these huge improvements - making SR-262 a safer corridor for everyone.

Guardrail Installation Efforts

SR-262 | Guardrail and Bridge Work | 02/26/26

 

WHAT'S HAPPENING NOW

 

Construction on the project is transitioning into the final phase of paving and finishing operations. On SR-162 between Montezuma Creek and Aneth, major earthwork activities are now complete, and crews are placing the final layers of asphalt pavement. This work is expected to be finished by the end of April.

On SR-162 from just east of Bluff to Montezuma Creek, crews are preparing to begin the final surface layer of asphalt in early May, with completion anticipated toward the end of May or early June, weather permitting. This final lift of pavement will complete the road structure and provide a smoother, more durable driving surface for the traveling public.

In addition to paving, crews will continue working throughout the corridor to complete fencing, guardrails, fiber installation, minor bridge work, signage, additional shouldering, and overall project cleanup. These activities are expected to continue through the paving period and into mid-summer. Drivers should continue to watch for intermittent lane shifts, reduced speeds, and flagging or pilot car operations in active work zones.

Paving Efforts in Aneth Utah

SR-162 Paving Operations | Between Montezuma Creek and Aneth | 04/15/26

 

TRAFFIC IMPACTS BY SEGMENT

 

SR-262 US-191 to Montezuma Creek (Complete)

All paving, guardrail installation, and roadside signage work are complete on this segment. No further construction delays are anticipated.

SR-162 Bluff to Montezuma Creek (Paving in Progress)

Final paving operations are scheduled to begin in early May.

  • Work will progress throughout the corridor, with completion anticipated early May.
  • Drivers should plan for occasional delays as work progresses.

SR-162 Montezuma Creek to Aneth (Use Caution)

  • Reconstruction earthwork is now complete.
  • Final asphalt paving expected to be completed by the end of April.
  • Use caution in active work zones and be prepared for flagging or pilot cars.

SR-162 Aneth to Colorado Border (Minimal Impact)

Occasional shoulder operations will occur as needed. No delays are anticipated on this segment.

 

 

CONSTRUCTION SCHEDULE

 

Work Days:  Mon - Fri (Except holidays), Sat as necessary
Hours: Sunrise to Sunset

Estimated Completion: Summer 2026 


Schedules are subject to change due to weather conditions and material availability. 

 

 

 
PROJECT DESCRIPTION

 

The Utah Department of Transportation (UDOT) will improve safety and pavement along 53 miles of road in San Juan county along SR-162 and SR-262.  Additional improvements include the rebuild of multiple structures, and other road specific enhancements. The following is a short list of several key upgrades: Improve and/or reconstruct pavement; Improve safety features such as guardrail, cattleguards, signage, pavement markings, widen or add shoulders; rebuild or improve several dozen culverts and flood prevention infrastructure, construct a roundabout at the SR-162 & SR-262 Intersection, replace the SR-162 bridge over McElmo Creek, and install fiber-optic conduit.

UDOT Project PIN# 17894

Know before you go. Check UDOT Traffic before hitting the road

 

UDOT has established a project-dedicated public involvement team for the SR-162 & SR-262 San Juan County Improved Project.  You can learn more or ask questions using the information below.

 

For More Project Information:

Hotline:  801-838-8364

Email: sr162-262@utah.gov

Project Website: udotinput.utah.gov/sr162-262

 

Safety Notice:

For your safety and the safety of those working in the area, please use extra caution, reduce speeds, and follow all posted signs and signals when driving through construction zones. Barrels and other traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.

 

Sent on behalf of Utah DOT by PublicInput.com
To subscribe, please share and send an email to sr162-262@utah.gov with "updates" in the subject line
 
Unsubscribe | My Subscriptions
 
View this email in a browser