Over the past two weeks, Street Division crews have made significant progress on the Patton Sidewalk Improvement project, here are the key updates:

Recent work completed:

  • 73 feet of sidewalk has been removed and replaced.

  • Sidewalks have been completed along the front of the following businesses:

    • Sweet Treats (77, 81 Patton Ave)

    • Empire Tattoo (83 Patton Ave)

    • Apotheca (85 Patton Ave)

    • Yacht Club (87 Patton Ave)

    • Sonora (89 Patton Ave)

Traffic control update:

  • On Monday, June 17, traffic control was extended down Patton Avenue.

  • This traffic control plan will remain in place for approximately 3 weeks (image below).

  • Crews will periodically reopen the lane in the afternoons and on weekends as work progresses.

map of traffic control area

Upcoming work (next 2 - 3 weeks):

  • Work will be focused in front of:

    • Public Service Building (91 Patton Ave)

    • Jack of the Wood (95 Patton Ave)

    • The building at 102 Patton Ave

  • This phase includes the removal of four trees, replacement of 152 feet of sidewalk and installation of a new curb ramp.

  • Coordination with adjacent property owners has been completed.

sidewalk calendar by coded colors

Access to Thirsty Monk:

  • Temporary access to Thirsty Monk at 92 Patton Ave remains in place.

  • Additional coordination with the property owner and business owner is ongoing.

  • A sidewalk detour ensures the area remains accessible.

Thank you for your continued patience and support as we work to improve the public infrastructure along Patton Avenue. If you have any questions or need further information, please do not hesitate to reach out.

Best regards,

Jessica Hughes
Communications Specialist
jhughes@ashevillenc.gov
City of Asheville

 

Sent on behalf of City of Asheville, NC by PublicInput
2409 Crabtree Blvd, Suite 107, Raleigh, NC 27604
Unsubscribe | My Subscriptions
View this email in a browser | 🌍 Translate