Welcome to the latest update on the Biltmore Village Infrastructure Recovery Project. We are excited to share several major milestones as we move closer to construction. Here is what’s happening and what you can expect next.
Historic Resource Commission has approved the design
We are pleased to report that the Historic Resource Commission voted unanimously to approve all applicable design items for the project.
Watch the meeting recording
City Awarded TDA LIFT funding
The City of Asheville was awarded $296,179 from the Buncombe County Tourism Development Authority’s Legacy Investment From Tourism (LIFT) Fund. The TDA Board voted to allocate the funds at their September 30 meeting, supporting LIFT Committee recommendations to fund pedestrian safety improvements at the intersection of Biltmore Plaza and Boston Way, out of an overall $2,289,054 funding request. These funds will be used to facilitate a crosswalk across Biltmore Plaza.
Bidding is now open
The official construction bid for the project has been posted! As an intentional step to ensure high-quality execution, we have pre-qualified contractors with specialized experience working in urban environments and brickwork.
View the bid documents on the Bid Posting page.
What’s next?
- Bids will be opened in November. Once reviewed, we will have a clearer, more finalized project scope to share and review with stakeholders. Before breaking ground, City Council is required to approve the construction contract.
- After selecting a contractor, we will host a dedicated pre-construction meeting to introduce the project team and walk through logistical details, impacts, and potential ways to mitigate disruption. Construction is expected to begin in early 2027.
Contracting in local government
North Carolina public procurement law requires the City of Asheville to choose the lowest responsive, responsible bidder for construction projects. This rule exists to protect taxpayers, prevent government corruption, and guarantee fair competition. It is the City's policy to provide equal opportunity to potential qualified bidders, and one way of achieving this is through outreach. When the construction bid is posted, we will share the opportunity with the community and invite neighbors to share.
Thank you for your continued patience and partnership as we move this critical recovery project forward!
|