| Welcome to the Corridor Program Construction Update!
The Corridor Mobility Program is the development, design, and construction of improvements along key Austin corridors that enhance mobility, safety, and connectivity for all users—whether you drive, walk, bike, or take transit. Prioritization of the improvements to receive 2016 Mobility Bond funding was guided by City Council’s Contract with Voters. Read on to stay updated on news, closures and impacts coming to your area.
| |
|
|
|
|
|
|
|
 |
| Intersection improvements coming to Airport Boulevard 'C1A' segment |
| |
|
|
|
|
|
|
|
 |
| Map of Burnet Road 'C2' segment: White Horse Trail to US 183 |
- Final Design and permitting ongoing. Construction is anticipated to start early 2026. Approximately 1.5 linear miles of corridor mobility improvements for Burnet Road from Bright Verde Way to Loop 1.
| |
|
|
|
|
|
|
|
 |
| East MLK Jr. Boulevard/FM 969 Corridor Construction project limits |
-
Design phase expected to wrap up early 2026. Improvements include dual sidewalk improvements up to Johnny Morris Road, raised median eastbound approaching Decker Lane, and signal upgrades at Craigwood and Decker Lane, including a new signal at Sendero Hills.
| |
|
|
|
|
|
|
|
 |
| Enhancements include the expansion to six-lane divided roadway from Mopac to Brodie Lane. |
-
Construction began this month. Community members are invited to Meet the Contractor, Smith Contracting Co., this Wednesday, July 16 at Bethany Lutheran Church.
| |
|
|
|
|
|
|
|
 |
| Improvements are coming to South Lamar Boulevard between Riverside Drive and U.S. 290 |
|
-
Project is in final design. Construction will consist of approximately three miles of corridor mobility improvements, including intersection improvements, like new and upgraded traffic signals, on South Lamar Boulevard from Barton Springs Road to US 290.
-
Phase two construction began this month. Construction is expected to last one to two months per phase, taking place in the right and left lanes, leaving the middle lane open for north and southbound traffic flow.
| |
|
|
|
|
|
|
|
 |
| The closure will last for several months as construction of the intersection is completed. |
| |
|
|
|