I-80 | Parleys Canyon Upgrade
CONSTRUCTION UPDATE
June 20, 2025

Thank you for your continued patience as crews began paving operations on the on- and off-ramps of I-80 last week. This weekend, crews will complete ramp paving, which will require intermittent ramp closures and a single lane closure in the area. Looking ahead to next week, we are reaching an exciting milestone: paving work on the main travel lanes will begin. To ensure the safety of our crews and deliver a smoother, upgraded road for you, two lanes will be closed at night, beginning as early as 7 p.m. Motorists should anticipate travel delays, particularly during peak travel hours.

Please refer to the Construction Activities and Traffic Impacts section below for more details. We truly appreciate your patience and cooperation as we work to improve I-80 through Lower Parleys Canyon.

 

New Pavement | Westbound I-80 on-ramp from SR-65 (Exit 134) | 06/19/25

 

 

SCHEDULE

 

 

Work Hours: Mostly Nighttime (7pm - 6am); Some Daytime work as necessary
Workdays: Tuesday Night - Sunday Night

Project Total Duration:  Approximately 75 days

Schedules are subject to change due to weather conditions and material availability.

 

 

CONSTRUCTION ACTIVITIES & TRAFFIC IMPACTS

 

  • Friday June 20th - Saturday June 21st:
    • Paving operations continue on eastbound and westbound ramps.
    • Nighttime ramps closures possible from Exit 132 - Exit 134. Detours posted using an alternate route of Exit 131 and Lambs Canyon (Exit 137).
    • Motorists can expect single lane night closures in both directions.

 

  • Starting Monday, June 23rd:
    • Paving Operations begin over the next few weeks and will require nighttime closures of two lanes in both eastbound and westbound directions starting as early as 7pm.
    • Barrels and cones will be used to safely guide vehicles into the open lanes during this work. 

 

 


 

PROJECT DESCRIPTION

The Utah Department of Transportation (UDOT) will resurface I-80, from Lower Parleys Canyon to SR-65 (exit 134). The project objectives are aimed at preserving the life of the road. This paving process will not only help increase the longevity of the road but also address roadway structural integrity and enhance motorist safety by providing a smoother, more durable road surface.  The on/off ramps along the route will also be resurfaced. Additional work includes variable drainage enhancements, barrier upgrades, and updated roadside signage and road surface striping.

Know before you go. Check UDOT Traffic before hitting the road

 

UDOT has established a project-dedicated public involvement team for the I-80 Mouth of Parleys Paving Project.

 

For More Project Information:

Hotline:  801-838-8362

Email: i80parleyspaving@utah.gov

Project Website: udotinput.utah.gov/i80parleyspaving

 

SAFETY NOTICE:

For your safety and the safety of those working in the area, please use extra caution, reduce speeds, and follow all posted signs and signals when driving through construction zones. Barrels and other traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.

 

Sent on behalf of Utah DOT by PublicInput.com