[ SEE PROJECT WEBSITE ]


SR-162/262 SAn Juan County Paving Logo

State Route 162 & 262 | San Juan County Improved | Energy Corridor
November 7, 2025

 

ROUNDABOUT OPENING SOON BUT WITH SAFETY FIRST

The crews working on the roundabout in Montezuma Creek are in their final throes of preparation before opening to the public! In recent months, crews have worked long hours to complete paving and permanent lane striping. Active work continues with the installation of the pedestrian sidewalk around the perimeter of the roundabout. To ensure safety before the official grand opening, roadside signs and road surface directional markings must be in place. This will be quickly followed by powering up and illuminating the area with the new LED downlights! If all goes according to schedule, we estimate traffic moving through the roundabout as early as January 2026. This will be the long-awaited milestone that allows our traffic management teams to eliminate the temporary bypass road that has been in service since early this year. It goes without saying that this structure will be a prominent landmark for the Montezuma Creek community! Stay tuned to our project website for additional details.

ROUNDABOUT DRIVING TIPS NOW ONLINE!

For many of you, we acknowledge that roundabouts may be a new travel experience.  We have provided a tutorial section on the project website devoted to demonstrating the safety enhancements and proper use instructions when traveling through roundabouts. While there, don't forget to check out the drive-through preview video!

Roundabout Looking East | SR-162/262 | 10/28/25

Thermoplastic Crosswalk Lines | Roundabout at SR-162/262 | 10/28/25

 

OTHER PROGRESS AND SOME IMPRESSIVE MILESTONES!

SR-162: 

Aneth to Montezuma Creek:  Crews continue the full reconstruction of the road along this stretch, one section at a time. It has certainly had the greatest impact on large transportation vehicles and requires a safety protocol that restricts all wide-load big rigs, as well as a minimum ground-clearance requirement for trailers. Reconstruction efforts along this stretch are approximately 60% complete and are anticipated to continue through the winter or until weather prevents further progress.

Top-to-Bottom Road Surface Reconstruction| SR-162; Montezuma Creek to Aneth | 10/28/25

Montezuma Creek to Bluff:  The bulk of the main paving along this stretch is complete, with the asphalt shoulder widening efforts recently completed. Plan on a final layer of paving along the stretch that will cap this work as early as next month. What remains are a few guardrail upgrades and off-road signage. Much of the work in 2026 will require minimal traffic control impacts.

McElmo Bridge:  While the approaches to the new bridge are still under construction, the bridge is structurally complete. A fresh polymer seal coating was recently applied to the bridge deck to reduce long-term corrosion and ensure a smooth ride for decades to come.

McElmo Bridge Photo Oct 2025

McElmo Bridge Aerial Photo Looking North | SR-162; Aneth | 10/28/25

SR-262: 

All paving activity is completed! Short distance flagging at prescribed locations will be required on this stretch to update guardrail and road signage.  That work will continue into the Spring of 2026.

 

LATEST TRAFFIC UPDATES

Plan on wide load restriction on SR-162 until further notice. this includes a minimum 12-inch clearance from ground level will remain in place. There are still varied short distance one-way alternating traffic operations using flaggers and a pilot car throughout the project.  Be prepared to come to a complete stop, be patient, and follow directions from our crews. Please plan on delays between 10-15 minutes or more during peak periods. 

We recognize that delays have occasionally been significant, but please understand the heaviest delays are behind us.  Motorist and crew safety is a commitment that remains paramount to UDOT objectives.  These traffic controls are thoughtfully planned to focus on maintaining safety FIRST while maximizing progress.  If you have any questions or concerns, we encourage you to contact our project hotline at any time.

 

CONSTRUCTION SCHEDULE

 

Work Days:  Mon - Fri (Except holidays), Sat as necessary
Hours: Sunrise to Sunset

Estimated Completion: Summer 2026 


Schedules are subject to change due to weather conditions and material availability. 

 

 


PROJECT DESCRIPTION

The Utah Department of Transportation (UDOT) will improve safety and pavement along 53 miles of road in San Juan county along SR-162 and SR-262.  Additional improvements include the rebuild of multiple structures, and other road specific enhancements. The following is a short list of several key upgrades: Improve and/or reconstruct pavement; Improve safety features such as guardrail, cattleguards, signage, pavement markings, widen or add shoulders; rebuild or improve several dozen culverts and flood prevention infrastructure, construct a roundabout at the SR-162 & SR-262 Intersection, replace the SR-162 bridge over McElmo Creek, and install fiber-optic conduit.

UDOT Project PIN# 17894

Know before you go. Check UDOT Traffic before hitting the road

 

UDOT has established a project-dedicated public involvement team for the SR-162 & SR-262 San Juan County Improved Project.  You can learn more or ask questions using the information below.

 

For More Project Information:

Hotline:  801-838-8364

Email: sr162-262@utah.gov

Project Website: udotinput.utah.gov/sr162-262

 

Safety Notice:

For your safety and the safety of those working in the area, please use extra caution, reduce speeds, and follow all posted signs and signals when driving through construction zones. Barrels and other traffic control devices are placed to guide motorists safely through the work zone, and to protect the project team.

 

Sent on behalf of Utah DOT by PublicInput.com
To subscribe, please share and send an email to sr162-262@utah.gov with "updates" in the subject line
 
Unsubscribe | My Subscriptions
 
View this email in a browser