Alternative 1 - 110378

 

Alternative 1 – East Side Widening along Westerville Road

  • Widen Westerville Road only on the east side in order to provide a second southbound left turn lane. 
  • Widen the north side of Morse Road to provide an exclusive westbound right turn lane.
  • Install a new span wire traffic signal to accommodate the pavement widening and additional load of the signal heads (with backplates). Includes modification of clearance intervals and optimization of signal timings.
  • Plane, resurface and restripe the existing roadway throughout the project limits.

 

 

Project Development Schedule

Start Detailed Design - Late 2020

Environmental Document Clear  - Summer 2021

Final Right of Plans  -  Summer 2021

Plan File  - Late 2022

Project Sale  - 2023

Begin Construction  - Spring 2023

 

Project Contacts:

ODOT Project Manager - Tracy Allen (Tracy.Allen@dot.ohio.gov or 740-833-8364).

ODOT District 6 Environmental Specialist - Amy S. Turner (Amy.Turner@dot.ohio.gov or 740-833-8240).