Tunnel Option

Converting US 17 to an underground tunnel would be an opportunity to reconnect neighborhoods that were divided in the 1960s. This option will allow reconnection of neighborhoods and cut-off cross-streets. The underground tunnel would also allow for a large park and/or a future bus rapid transit line where US 17 is now. However, it will be expensive and complex to construct and would require large ongoing maintenance costs. Based on the traffic analysis, moving US 17 underground would require three lanes of through traffic in each direction. The conceptual route for the proposed tunnel is shown on the aerial photograph below. Also, the tunnel would have an upper and lower level with northbound and southbound traffic on different levels. The US 17 design would need to meet SCDOT design criteria, so it could not follow the existing roadway exactly. 

The tunnel option is technically challenging. The tunnel must avoid the 2006 "Ashley Tunnel" sewer system owned by the Charleston Water System. The tunnel must avoid the US 17 Septima P. Clark Parkway Transportation Infrastructure Reinvestment Project. The 40 foot-wide right-of-way of the deep underground drainage tunnel generally follows the alignment of US 17. It is assumed that deep foundations will not be permitted near the deep tunnel right-of-way.  

 

Simulation Video of the Tunnel Option (no sound)

Elevated Option

The second option to increase the capacity of the Septima P. Clark Parkway would include elevating the roadway from the Ashley River to I-26. This option would also provide an opportunity to reconnect the community with a large park and/or a future bus rapid transit line where US 17 currently exists. An elevated roadway could be easier to construct and less expensive than a tunnel. Based upon the traffic analyses, elevating US 17 would require three lanes of through traffic in each direction. The plan view of the elevated highway and its cross-section are shown on the aerial photograph below.

Simulation Video of the Bridge Option (no sound)

Summary of Environmental Effects

This table summarizes the potential environmental effects the options for adding capacity to the Septima P. Clark Parkway. In the analysis, the US 17 team considered twenty-nine potential environmental effects. The table summarizes the differences between the two options. 

 

SEPTIMA P. CLARK PARKWAY

 

 

OPTION A

 

OPTION B

 

 

Underground  

 

Elevated

 

 

 

 

 

 

 

 

 

 

 

HUMAN ENVIRONMENTAL FACTORS

 

 

 

 

Relocations – residential units

 

92

 

130

Relocations – non-residential properties

 

16

 

25

Total number of relocations

 

108

 

155

Land acquisition (in acres)

 

17

 

25

Conversation area

 

0

 

0

Schools

 

1

 

1

Parks

 

3

 

3

Greenways

 

2

 

1

Community Facilities

 

6

 

5

Neighborhood Cohesion

 

The tunnel option may improve community cohesion by reconnecting neighborhoods.

 

Residents may see land beneath the bridge as unusable.

Environmental Justice

 

There may be temporary construction-related Environmental Justice impacts.

 

The Bridge Option may have long term Environmental Justice impacts.

Historic Architectural Resources

 

4

 

4

Archeological Resources

 

1

 

1

Compatibility with zoning and land use plan 

 

Yes

 

No

Traffic noise

 

Traffic noise has not been analyzed

 

Traffic noise has not been analyzed

Visual / Aesthetic

 

The aesthetics of a tunnel will be a change

 

The aesthetics of a bridge will be a change

Recognized Environmental Conditions (RECs)

 

5

 

5

Utility Conflicts

 

The tunnel must avoid the Charleston Deep Drainage Tunnel

 

Unknown

Permits needed

 

Yes

 

Yes

Construction cost – opinion of probable cost

 

$500,000,000

 

$275,000,000

 

 

 

 

 

NATURAL ENVIRONMENTAL FACTORS

 

 

 

 

Threatened Endangered Species

 

No Effect

 

No Effect

Essential Fish Habitat

 

No Effect

 

No Effect

Section 404 Waters of the US – wetlands

 

No Effect

 

No Effect

Section 404 Waters of the US – streams

 

No Effect

 

No Effect

Land and Water Conservation Fund sites (section 6f)

 

No Effect

 

No Effect

US Navigable Waters – rivers and open water

 

No Effect

 

No Effect

US Navigable Waters – critical area wetlands

 

2 Acres

 

0 Acres 

Prime Farmland

 

0

 

0

 

Question title

Please select one of the following options for improving the Septima P. Clark Parkway.

Tunnel Option
44%
Bridge Option
31%
Do Nothing
25%
Closed to responses | 112 Responses