2022-2027 Bond Project: Brackenridge Park LF
2022-2027 Bond Project: Brackenridge Park LF
Brackenridge Park Leverage Fund (2022-2027 Bond Project): The City of San Antonio's Public Works Department will complete construction of 2017 Bond projects and further development of the adopted Park Master Plan within available funding at Brackenridge Park.
Project Type: Parks & Recreation
Phase: Design
Project Manager: Jamaal Moreno, Jamaal.Moreno@sanantonio.gov
Estimated Construction Timeline: Winter 2027 - Fall 2028
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Parks) | $2,500,000.00 |
Total | $2,500,000.00 |
Related projects:
2017-2022 Bond Project: Brackenridge Park
2022-2027 Bond Project: Brackenridge Park Facilities LF
Brackenridge Park Facilities Leverage Fund (2022-2027 Bond Project): The City of San Antonio's Public Works Department will construct general park improvements which may include leveraged funding towards the renovation of the historic Sunken Garden Theater Facility and Brackenridge Park at Brackenridge Park.
Project Type: Parks & Recreation
Phase: Project Initiation
Project Manager: Jamaal Moreno, Jamaal.Moreno@sanantonio.gov
Estimated Construction Timeline: Fall 2025 - Winter 2027
Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).
Project Budget: | |
2022 General Obligation Bond (Parks) | $5,000,000.00 |
Total | $5,000,000.00 |
Events
2022-2027 Bond Project: Brackenridge Park LF - Open House
Brackenridge Park Phase II (2022-2027 Bond)
You're Invited!
Join Capital Delivery, Parks & Recreation, and Council Districts 1 and 2 for an open house showcasing the completed Brackenridge Park Phase II Project design.
Visit anytime from 5:30pm to 7:30pm to review the final plans and chat with the design team.
Brackenridge Park Phase II Project Open House Invitation
If you require translation services, please notify us 72 hours in advance of the meeting.
NOTE TO BUSINESS OWNERS:
If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.
Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.