Thank you to those that joined the virtual public meeting Wednesday May 6, 2020 from 4-6pm.  

The meeting explained the overall bridge project, presented the proposed new bridge design and aesthetics, and discussed the proposed detour route during construction expected in 2024.  Please click on the handout and exhibits.  Also, watch the presentation here.    

 

Please let us know your questions and comments through June 5, 2020!  

Push "Continue" below for all the different ways to submit questions and comments!   

complete
complete
May 6, 2020

Online Public Meeting

complete
complete
June 5, 2020

Comment Period ends

planned
planned
May 2020-December 2021

Preliminary and Detailed Design

planned
planned
May 2020-August 2021

Environmental Clearances

planned
planned
March 2021-December 2022

Right of Way Acqusition 

planned
planned
October 2023

Sale of Project 

planned
planned
Spring/Summer 2024

Construction