Thank you for those that joined us for a virtual public meeting! 

 

The meeting presentation (click here or view at the bottom of the page) explains the overall bridge project, presents the proposed new bridge design, and discusses the proposed detour route during construction expected in 2022. 

Please click on the handout and exhibits for additional information.  

 

Si desea que los materiales para esta reunión son traducidos a español, contacte a Victoria Beale tan pronto que sea posible a Victoria.Beale@dot.ohio.gov o por teléfono a 614-466-3129.

إذا كنت ترغب في ترجمة مواد هذا الاجتماع إلى هذه اللغة، فلا تتردد في الاتصال بـ Imad Bdeiri في أقرب وقت ممكن عبر Imad.Bdeiri@dot.ohio.gov (٤١٩٣٧٣٤٤٥٦419-373-4456).

 

 

Please let us know your questions and comments through July 10, 2020!  

Push "Continue" at the bottom of this page for all the different ways to submit questions and comments!   

complete
complete
June 10, 2020

Virtual Public Meeting 

4-6pm

complete
complete
July 10, 2020

Comment Period Ends

planned
planned
August 2020

Environmental Approval expected

planned
planned
Fall 2020

Detailed Design starts 

planned
planned
Late 2020-Early 2021

Right of Way Acqusition 

planned
planned
Spring 2022

Construction starts 

21 day closure of Reynolds Road during the 4 month construction