You can find more information about the Point of Rocks Phase II project in the County Spotlight video, included below! 

Question title

For those who would like to submit any comments to the County, feel free to provide your comments/feedback here:

complete
complete
100% Design Plans

Based on regulatory agency feedback, the Design Team adjusted the design plans to decommission the pond, provide pocket wetlands, stream restoration, reforestation, and provide a new pedestrian bridge between Bank Street and Gibbons Road. 

complete
complete
June 2021 - Virtual Public Meeting

The Design Team virtually presented the 100% Design Plans to the community on June 23, 2021. Feedback was accepted through July 2, 2021. The Design Team incorporated feedback from the meeting by including a pedestrian bridge in the final design plans. 

complete
complete
October 2023 - FEMA Grant Award

After working through the design review process with FEMA, the County was notified in October 2023 that they were awrded a Pre-Disaster Mitigation Grant totaling almost $900,000. This grant funding will not only offset the cost to the County, but will allow for additional work to be completed upstream of the original project design.

The Design Team has cooperated with FEMA to address their questions pertaining to the Environmental Assessment (EA) process for this project. The EA was posted for public comment from July 21, 2023 to August 20, 2023 with no public comments received. 

complete
complete
November 2024 - Project Construction

Construction began in the middle of November, 2024. The County held a pre-construction meeting with the construction contractors and design engineers the week of November 11. 

complete
complete
March 2025 - Dam Removal

complete
complete
May 2025 - Pedestrian Bridge Installation

complete
complete
June 2025 - Planting and Landscaping

Work included placing topsoil and planting over 250 trees, over 800 shrubs, and seeding 1.5 acres of the project area with an upland meadow seed mix.

Installation of a mulch trail and reconstruction of a small footbrige providing access from Gibbons Road to the large pedestrian bridge spanning the stream channel. 

complete
complete
July 2025 - Construction Complete

live
live
Warranty Repair Work

Repairs are being completed the week of November 10, adjusting a rock structure downstream of the pedestrian bridge. These repairs are being completed to ensure proper conveyance of stream flow, and they do not have any impact on stability of the bridge. The construction crew will access the stream from Bank Street.