Last Updated:  9/13/22

2022 Construction Schedule

Estimated Start Date:  Monday, August 22

Construction Days:  Monday - Friday (Updated)

Construction Hours:  7am - Sunset

Construction Duration:  mid-October; 45 and 60 day duration

 Traffic Impacts:  Please see the "Project Map & Traffic Control" Tab above

 

Note: Schedules are subject to change due to weather and materials available


Forecast Work Details:  (See "PROJECT MAP & TRAFFIC CONTROL"  Tab for traffic impacts)

  • Reconstruction of the travel lanes and shoulders begins August 22 to accomodate the road widening efforts along the West side of SR-30
  • Crews will shift & rebuild bicycle path, but bicyclists traffic along pathway will be maintained
  • Paving work is expected to begin Thursday, October 6
  • Signs and temporary travel lane paint lines will be installed starting Monday, October 10 through Friday, October 14
  • Operations will conclude by mid-October, then resume in June 2023 for a couple of weeks to complete a chip seal coat and final pavement markings.

Safety Notice:

For your safety, as well as the safety of the working in the area, please use extra caution and stay alert while driving through construction zones.  Businesses and residents in the area should anticipate increased noise, dust, and vibration associated with construction.

UDOT PROJECT INFORMATION PAGE


LATEST TRAFFIC CONDITIONS

udottraffic.utah.gov 

or download the latest UDOT Traffic App.


FOR IMMEDIATE PROJECT INQUIRIES

Jeffrey Putzke, Public Involvement Manager

Meteorologist

Phone:  801-652-4008

Email:  [email protected]