PROJECT UPDATES

 

06/05/2023 -  Construction Information and Other Relevant Info

Lyon Court Connector - Fiber Bridge Construction

  • Estimated Construction Completion: Summer 2023 (Updated)

  • (Reminder) Site safety etiquette and processes will be enforced by the construction supervisors and crew. Residents, pedestrians and cyclists are to exercise caution around the construction area. Residents should anticipate construction sounds/noises and impacts to traffic along and near Lyon Court and Veteran Lane.


General Contractor: HALL CONTRACTING CORPORATION
In Case of Construction Emergency Call 980-771-3216

 

 

03/13/2023 -  Construction Information and Other Relevant Info (Updated 3/22/23)

Lyon Court Connector - Construction Notice #2

  • Construction resuming no later than March 31, 2023

  • Estimated Construction Completion: Spring 2023

  • Site safety etiquette and processes will be enforced by the construction supervisors and crew. Residents, pedestrians and cyclists are to exercise caution around the construction area. Residents should anticipate construction sounds/noises and impacts to traffic along and near Lyon Court and Veteran Lane.

    • Note: Pile Driving is restrictied to daylight hours between 8am and 4pm effective March 23, 2023.


General Contractor: HALL CONTRACTING CORPORATION
In Case of Construction Emergency Call 980-771-3216

 

Calendar Year 2022 -  Estimated Project Schedule

*UPDATE: CONSTRUCTION DURATION ~ SUMMER 2022 - EARLY 2023*

PLAN

Lyon Court Connector Plan & Profile Condensed

Note that this plan shows preferred recommendations, which are subject to change based on design and budget considerations. 

General Information:

Why is this bridge being installed?

This pedestrian bridge was a requirement for the development of the Veteran Lane apartments and was initiated in 2015.  The developer provided funds for the County to install the bridge.  The bridge installation was delayed due to the City of Charlotte Storm Water project along Lyons Court.  Design, permitting, and logistics were restarted upon completion of the City Storm Water Project.

 

What kind of bridge will be installed?

The bridge will be a pedestrian/bicycle bridge only.  The bridge will be a modern polymer, light weight bridge with an 8 foot wide travel lane.  Bollards will be placed on each end to prevent any vehicular traffic from attempting to cross. 

 

Will this bridge impact any FEMA floodplains or wetland areas?

No.  The small stream is not a designated FEMA floodplain.  An environmental impact study was produced for this project and it did not indicate the presence of wetlands in this area.   The proposed pedestrian bridge is being installed in an area of previous construction activities.  

 

What about increased trash from pedestrians?

Mecklenburg County Park and Recreation will be responsible for maintenance of the bridge and surrounding areas.  A permanent trash receptacle will be installed on the Lyon Court side of the bridge.  There are existing trash cans on the Veteran Lane side of the project.

 

Who is paying for the bridge?

Funds for the purchase and installation of the bridge were received from the developer of the Veteran Lane apartments in 2015.  These funds will cover most of the project.  Any additional funds will be drawn from the Mecklenburg County Park and Recreation Capital Fund.

 

Can the construction of the bridge occur from the Veterans Lane side of the project?

No.  Construction access will be from Veteran Lane and from Lyon Court.  Traffic control plans are included in the final plan set.

 

How long will it take to complete construction?

Anticipated construction duration is six to eight months. Start of construction is tentatively scheduled for Mid 2022.

Question title

Do you have any additional comments or questions about the project?

Question title

* Would you like to provide your contact information for future project updates?

Additional questions? Contact:

Robert Billings, Project Manager

Robert.Billings@mecklenburgcountync.gov or 704-572-7813

 

Darneka Waters, Planner

Darneka.Waters@mecklenburgcountync.gov or 980-722-2291