The City of Asheville has posted a Request for Qualifications (RFQ) to hire a team of qualified design and engineering professionals who will design this project. 

Next Milestone: Design Phase

Background

This project will install a continuous sidewalk on the north end of London Road from Belvedere Road to Sweeten Creek Road, improving connectivity between the residential Shiloh area and the commercial and industrial areas on Sweeten Creek Road and in Biltmore Village. The purpose of this project is to improve mobility, safety, and continuity for pedestrians on City streets and provide pedestrian connections to important commercial and public amenities. 

The project also includes curb ramps, crosswalks, accessible bus boarding areas, and stormwater infrastructure upgrades.

london road sidewalk

 

Frequently Asked Questions

This project is funded by the voter-approved 2024 General Obligation Bond referendum.

The City recognizes an opportunity to improve safety on London Road in its entire length. At this time, there is no funding allocated for future phases. Starting at the north end of the road allows for continuous pedestrian connection. The City appreciates any feedback from the community on potential future improvements southward on London Road.

Let’s connect! Please contact the Project Manager at jweissman@ashevillenc.gov. Anyone who is interested in this project is encouraged to subscribe for email updates at the top of this project page.

live
live
Advertise and Select Design Firm

planned
planned
Design Phase

Estimated timeframe: 2025 - 2026

planned
planned
Construction

Estimated to begin in 2027

complete
complete
Planning Phase

  • GAP Plan adopted in 2022

  • GO Bond approved by Voters in November 2024

  • Staff research and development

Contact 

Jill Weissman, Project Manager

jweissman@ashevillenc.gov 

828-989-3289