Overview of Project

IA 14 from south of N 4th Avenue W to north of High Avenue in Newton will be reconstructed. Improvements include:

  • PCC reconstruction of the 24-foot wide roadway with 10-foot shoulders (6-foot paved and 4-foot granular).
  • All work will occur in the existing right-of-way; no additional easements or property are needed for the project.

IA 14 will be closed at this location during construction and a detour will be used. The proposed official detour will use Interstate 80, Iowa 224, and County Rd F17. The contractor will work with property owners in the project area to maintain access to their property.

Map of the Project

Map of Newton Iowa showing Iowa 14 and U.S. 6 and 1st Ave E

Schedule

PhaseDate
DesignWinter 2024 through Spring 2026
LettingJuly 21, 2026
ConstructionFall 2026 to Late Fall 2027