Project Timeline

complete
complete

APD Strategic Planning Kickoff: November 2022

complete
complete

Strategic Planning Committee Prep Work: December 2022 to June 2023

complete
complete

– Internal Stakeholder Listening Sessions: April 2023 to June 2023

complete
complete

Community Input Sessions: June 2023

complete
complete

Leadership Retreats and Framework Development: July 2023 to August 2023

complete
complete

Community Input Session and Survey: September 2023 to October 2023

complete
complete

Goal and Strategy Development: October 2023 to January 2024

complete
complete

APD Strategic Plan Leadership Adoption: February 2024

complete
complete

Strategic Plan Document Preparation and Rollout: February 2024 to April 2024

planned
planned

Strategic Plan Implementation: February 2024 to Ongoing

planned
planned

Measure Development: March 2024 to August 2024