In 2014, Grand Rapids voters established the Vital Streets fund. This fund dedicates its focus to improving our street conditions. The Buchanan Avenue project from Stewart to Corrine is funded by Vital Streets. 

About the project

Buchanan Avenue (Stewart to Corinne)

Construction is expected to start in 2028. 

This is a reconstruction project. Contractors will replace the road and upgrade what is listed below:

  • Watermain replacement and lead water service line replacements
  • Driveway approaches and sidewalks
  • Complete the bicycle connection on Buchanan from Stewart to Corinne
  • Parking changes
  • Pedestrian crossings at key locations to improve safety
  • Street trees 

Check out our Road Construction Guide to learn more.

Have a question?

Contact Us 

communityengagement@grcity.us

311 or 616-456-3000

Timeline

Project Timeline

planned
planned

December 2026 or January 2027: Concept Design Meeting

At this open house we will share the proposed concept design. The design includes extending the bicycle facilities to complete the connection to the facilities on Buchanan to the north. 

 

planned
planned

2028: Construction Begins

planned
planned

2028: Construction Ends