Buchanan Avenue (Corinne to Hall)

Construction is expected to start in September.

This is a reconstruction project. Contractors will replace the road and upgrade what is listed below:

  • Driveway approaches and sidewalks

  • Water

  • Parkways and street trees

  • Storm sewer

Check out our Road Construction Guide to learn more.

Project Limits and Detour

 

Have a question?

Contact Us 

communityengagement@grcity.us

311 or 616-456-3000

Timeline

planned
planned
August: Construction Preparation Meeting

At this meeting we will share the work to be completed, project schedule, and access during construction.

 

planned
planned
September 2026 Construction Begins

The detour uses

 

planned
planned
November 2026 and Spring 2027: Construction ends

Construction is expected to occur in two phases. Phase 1 is September - November 2026. Phase 2 will be in Spring 2027.