Virtual Open House

Public involvement is an important part of the development of this project, and input from the community will help guide decision-making. ODOT’s goal for this virtual Public Open House is to share information about the project and gather your feedback.

 

HOW THIS SITE WORKS

This site is a self-guided tour through a series of tabs that highlight key information about the proposed project. To advance between tabs, click on the green CONTINUE button located at the bottom of each page. You can also move between pages by clicking the tabs located at the top of the discussion section. If you would like to view larger versions of any of the images or charts, simply click on them. Copies of project materials and related documents are posted under the DOCUMENTS section, located on the right-hand side of the screen.

 

COMMENTS

The official comment period for this project has ended. However, you can still provide feedback or ask questions by contacting the ODOT Project Manager using one of the following contact methods:

Ohio Department of Transportation District 8 Office

Attention: Garrett Tout, P.E.

505 South State Route 741

Lebanon, OH 45036-9518

Telephone Number: (513) 933-6699

E-mail: Garrett.Tout@dot.ohio.gov

Please reference WAR-22-0.00 (PID 116337) in all communications.

All comments carry equal weight, no matter how they are submitted. Public participation is solicited without regard to race, color, sex, age, national origin, or disability. 

 

The environmental review, consultation, and other actions required by applicable Federal environmental laws for this project are being, or have been, carried-out by ODOT pursuant to 23 U.S.C. 327 and the Memorandum of Understanding dated May 8, 2026 and executed by FHWA and ODOT and the Memorandum of Understanding dated December 3, 2024, and executed by FRA and ODOT.

For more information, visit ODOT's NEPA Assignment Portal by clicking here.

How did you hear about this project?

Postcard in Mail
57%
Social Media
34%
Word of Mouth
9%
Other
2%
Newspaper / Online / TV News
0%
Closed to responses | 498 Responses

Project Timeline

complete
complete

Virtual Public Open House

The formal comment period ended on July 29, 2026. However, comments submitted after July 29, 2026 are still welcome and valued.

live
live

Environmental Documents Completed

Summer 2026

planned
planned

Detailed Engineering Design

Fall 2026 through Summer 2027

planned
planned

Right-of-Way (Land Acquisition)

Summer 2026 through Summer 2027

planned
planned

Engineering Plans Completed and Project Sale/Award to Contractor

Fall 2027 through Winter 2028

planned
planned

Construction

Spring 2028 through Fall 2028