Progress Village Regional Drainage Improvements

Progress Village Regional Drainage Improvements

Welcome to the public information page for the Progress Village Regional Drainage Improvements project. Comments are open from June 18, 2024, to July 1, 2024. An open house will be held at 6:30 p.m., Tuesday, June 18, 2024, at the Emanuel P. Johnson Recreation Center, 5855 S. 78th St., Tampa, FL 33619.

 

Overview

Overview

Hillsborough County Capital Programs has scheduled a stormwater improvement project in the Progress Village area. This project is necessary to reduce roadway flooding and improve overall water quality.

Drainage Improvements

  • Installation of new stormwater drain under Ash Avenue and South 83rd Street that proceeds south along South 83rd Street and under Progress Boulevard

  • Replacement of existing drainage inlets and outfalls south of Progress Boulevard in an existing, County-owned easement that runs between houses toward Archie Creek and crosses Allamanda Avenue, Bahia Avenue, Croton Avenue, Dahlia Avenue, and Endive Avenue

  • Connection to a water quality treatment dry pond south of Endive Avenue and north of Lamb Elementary School

  • Floodplain compensation in an area south of Archie Creek

  • Roadway and pavement improvements will include localized pavement resurfacing centered around drainage pipe crossings

Project Overview

Progress Blvd

Ash Ave

 

Dahlia Ave