2022-2027 Bond Project: Babcock Road (West Hausman to UTSA Boulevard)

2022-2027 Bond Project: Babcock Road (West Hausman to UTSA Boulevard)

The project will construct roadway improvements to include sidewalks, curbs, driveway approaches, drainage, and other improvements as applicable and within available funding.

Project Type: Streets, Bridges, & Sidewalks

Phase: Design 

Project Contact: Katherine Schneider - (210) 207-8549

Estimated Construction Timeline: Spring 2026 - Winter 2027

Estimated Timeline Construction Seasons are identified as: Winter (January, February, March), Spring (April, May, June), Summer (July, August, September), and Fall (October, November, December).


Project Budget:

 

2022 General Obligation Bond (Streets)

       $10,000,000.00

CPS Energy

              $272,567.00

San Antonio Water System

             $211,861.00

Tree Preservation Fund

               $500,000.00

Total

        $10,984,428.00

 

 

 

 

 

 

 

 

 


Project Limits: 

 

What you need to know:

E-Z Bel Construction is continuing to make roadway and sidewalk improvements along Babcock Road.

Upcoming Work & Traffic Changes:

Starting as early as Wednesday, September 2, 2026, traffic will shift to the east side of Babcock Road so crews can begin construction on the west side. This phase is expected to last through the end of 2026.

Traffic Details:

  • The southbound lane on the west side of Babcock Rd. will be closed.

  • Traffic will remain open in both directions at all times.

  • The west sidewalk along Babcock Rd. will be closed between Hausman Road and UTSA Boulevard. A dedicated pedestrian path will be available starting at the middle of the block and heading north toward UTSA Boulevard.

  • Access to all neighborhoods, businesses, schools, and UTSA will remain open.

  • Street parking is strictly prohibited within the active construction zone.

  • Please follow all traffic signals, reduced speed limits, and digital message boards when driving through the area.

Thank you for your patience and cooperation as this project continues.

Babcock Road - Work Zone Map and pedestrian Detour

Babcock Road - Work Zone Map 

 

Babcock Road East View

Babcock Road & UTSA Blvd - Southview  

 

Babcock Road South View

Babcock Road - Southview 

 

Babcock Road North View

Babcock Road - Northview

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Contact Information

To receive project updates and details on future public meetings, please provide the following information.

Please share any feedback or questions about this project.