Happening Now

A field assessment is underway to review the extent of damage to lighting infrastructure in Biltmore Village. Upon completion of the assessment, a final report will be produced, which will inform construction timeline and cost. 

Background

On September 27, 2025, Tropical Storm Helene struck Asheville, bringing record-setting rainfall and widespread flooding. The storm caused the most extensive flooding in Asheville’s recorded history. In Biltmore Village, floodwaters rose high enough to submerge streetlights for several days, leaving poles filled with mud and damaging underground utility systems.

After Helene, community members around Biltmore Village identified safety and economic recovery as top concerns. Many businesses are experiencing economic hardship and want to make the most of increased foot traffic and tourism during the summer. Lighting plays a key role in safety for:

  • Tourists and shoppers

  • Biltmore Village tenants and employees

  • Residents and commuters

  • Pedestrians and cyclists

City of Asheville staff, in coordination with Biltmore Village business owners, put temporary lighting solutions in place shortly after the storm. The long-term fix requires full restoration and evaluation of damaged infrastructure. 

Funding and Overall Recovery Strategy

The City of Asheville is sequencing recovery projects strategically to ensure an efficient and effective rebuilding process. Cost recovery through federal disaster relief funding programs is essential in making this project possible. The City of Asheville seeks to accomplish this project primarily through the FEMA Public Assistance Program. Additional funding sources may later be identified. 

The kick off of the Biltmore Village Lighting Recovery project follows RFQ postings for rebuilding the French Broad Riverfront, repairs to the Municipal Golf Course, and a project to improve water treatment plants. Alongside these relatively complex projects, smaller repairs are being made to other City-owned parks, streets, and facilities. Active examples include roof repairs to the Municipal Building and Thomas Wolfe Auditorium.

In conjunction with storm recovery efforts, the City continues to advance its Capital Improvement Plan as well as bond projects. The integration of these initiatives ensures a coordinated effort to strengthen Asheville’s infrastructure and economic stability.

 

live
live
Field Assessment

Field assessment work began in January 2026 and is expected to be complete in early 2026. A final report will be produced upon completion of the assessment. 

planned
planned
Construction Phase

Timeline is to be determined by the field assessment.

complete
complete
Install Additional Temporary Lighting

Completed in fall of 2025.

complete
complete
Advertise and Select Contractor for Assessment

A Request for Qualifications was posted on April 9, 2025. City Council approved of a contract on August 26, 2025.

complete
complete
Temporary Lighting Installed

Completed in December 2024.

Contact

Chris Cairns

Traffic Engineer 

City of Asheville

ccairns@ashevillenc.gov