PROJECT UPDATE:

 
November 27, 2024
 

We are currently focused on site prepping sidewalks and headwalls, along with placing the crushed rock flexible base material from Casina Springs to Oakland Road. The team is conducting excavation of Network Road in the north bound lane and installing the curb inlet at Network (east side) as well as 30 inch storm drain lateral connection at Laureate. 

The concrete contractor is prepping and placing sidewalks in the locations noted as we complete the sidewalk grading, and there is some water meter adjustment in the working area.

Our current estimate for completion is early 2025.

 

PLANNED UPCOMING ACTIVITIES:

  • 11/26/2024 - 12/02/2024: 
    • Fox Quality Concrete completed curb and gutter installation and continues work on the  Shared Use Path construction. Concrete curb installation  between Babcock and  Woodwaters Way
  • 12/02/2024: 
    • JDA completed 10" base course and will start on surface pavement from Babcock Rd to Venado Trace on the week starting after curb installation is complete 
    • JDA will begin removal of barrier and traffic will be diverted to the outside lanes

  • 11/26/2024 - 12/02/2024: 
    • JDA completed 10" base course of  paving between Woodwaters and Laureate with exception of the Network intersection
    • JDA will begin removal of barriers starting the week of 12/02/2024 and traffic will be diverted to outer lanes
    • Continue work on surface course on the week starting on 12/2/2024 after barriers are removed and concrete curb is installed at various locations
  • 11/26/2024 - 12/10/2024: 
    • Fox Quality Concrete poured the curb and gutter, and will continue with the installation of the Shared Use Path and driveway construction between Woodwaters and Laureate
  • 12/04/2024: 
    • JDA will continue reconstruction of the east half of the Network intersection and Network transition with flex base and placement of ashpalt
    • JDA finalizing the flex base placement and preparing for asphalt paving between First Chinese Baptist Church and Laureate; placed no construction traffic signage at First Chinese Baptist Church

 

 

  • 11/26/2024: 
    • Outfall C drainage continues from just south of Lockhill north toward Prue Road
  • 12/09/2024:
    • Lockhill closes to through traffic between Southwell and Oakland - drainage construction starts; detour via Prue Road or Hollyhock
  • 12/09/2024: 
    • Outfall C drainage continues between Verbena and Hollyhock

 

 

**PLEASE NOTE: ALL WORK IS SUBJECT TO FAVORABLE WEATHER CONDITIONS**


 

 

 

 

NOTE TO BUSINESS OWNERS:

If your business is currently or expected to experience construction in your area please visit the City of San Antonio's Construction Toolkit. This guide helps business owners understand and prepare for City-initiated construction projects.

Business Outreach Specialist: 210-207-3922, smallbizinfo@sanantonio.gov


Learn more about City projects in your neighborhood and across San Antonio. The City of San Antonio’s digital dashboards encompass a wide range of projects, including streets, drainage, parks, and facilities.


 

Question title

To receive project updates and details on future public meetings, please provide the following information.

Question title

Please share any feedback or questions about this project.

 


Excavation work continues on the north side of Prue Rd. looking West.

 

 

Excavation work and Box Culvert installs continue on the north side of Prue Rd. looking West.

 

 

Utility installation work on the north side of Prue Rd. looking East.