Data Centers (TC-7-26)
Data Centers (TC-7-26)
Data Centers (TC-7-26): The Raleigh City Council approved a temporary six-month pause of development approvals for certain data centers at its Oct. 6 meeting. This pause has allowed the City to study the unique impacts of major data centers on surrounding properties and the City’s resources and adopt regulations to address those impacts. Under current North Carolina law, the City’s Unified Development Ordinance (which guides how land and buildings are developed, see below) cannot ban data centers.
During this time, City staff, including the Planning and Development Department, have drafted this proposed UDO text change to mitigate impacts of data centers. Read the draft ordinance.
What is a data center?
A data center is a facility that houses computer systems used to store, process, and manage digital information. Data centers help power many of the online services people and businesses use every day. Data centers typically have infrastructure such as air handlers, power generators, and cooling systems to ensure continuous operation. In Raleigh, larger data centers can only be built in certain places and require a special permit (see below). The moratorium pauses that application and review process.
What kinds of data centers does Raleigh allow?
There are two types of data centers:
1. Minor data centers
Classified as Minor Utilities under the City’s Unified Development Ordinance, these small facilities are 10,000 square feet or less with low peak electrical demand and water use. They have minimal impact and are allowed in all zoning districts.
2. Major data centers
Classified as Major Utilities under the City’s Unified Development Ordinance, these larger facilities include the big “hyperscale” centers seen in the news. These can only be built in industrial zones and must go through a Special Use Permit process.
Current Rules
Currently, the UDO contains provisions allowing smaller data centers that support businesses and digital services in all zoning districts, while Major Utility data centers (those exceeding Minor Utility thresholds) are permitted only within Industrial Mixed Use (IX) and Heavy Industrial (IH) zoning districts and require approval of a Special Use Permit by the Board of Adjustment. Through an evidentiary hearing, the applicant must demonstrate compliance with applicable UDO standards and compatibility with surrounding uses.
Proposed Draft Ordinance
As proposed, this text change will:
- Codify and clarify data center regulations: Establish definitions and classifications for data centers, distinguish between Minor and Major Data Centers.
- Establish performance and design standards: Create new requirements addressing noise, vibration, lighting, mechanical equipment screening, buffering, generators, and other potential impacts on surrounding properties.
- Require additional environmental and infrastructure review: Require pre- and post-development studies and assessments addressing water and wastewater capacity, stormwater, hazardous materials, energy demands, noise, vibration, and cumulative impacts.
- Strengthen operational and public safety requirements: Establish standards for generator operation and testing, battery storage safety, emergency contact information, hazardous materials management, and facility abandonment and decommissioning.
Public Meeting Schedule:
This text change is scheduled for a Planning Commission meeting on December 8, 2026. We will be collecting comments here through November 30. Comments after this date should be submitted directly to Justin Bucher via email at Justin.Bucher@raleighnc.gov.