Fulton Street (Plymouth to Worcester)

Construction is expected to start at the end of March 2026. 

The project will install sidewalks on the north side of Fulton Street from Plymouth Avenue to Worcester Drive.  This work will require some tree removals. New trees will be planted with the project.

This will fill in the gap in the sidewalk network and provide transportation choices for people. The sidewalks will be installed on City property.

After the project is complete, property owners are required to:

  • Clear sidewalks within 24 hours from the time it stops snowing. 
  • Maintain the parkway. The parkway is the area between the sidewalks and road.

 

Project Limits 

 

Have a question?

Contact Us 

communityengagement@grcity.us

311 or 616-456-3000

Timeline

planned
planned
March 19: Construction Preparation Meeting

At this meeting we will share the work to be completed, project schedule, and access during construction.

 

Register Here

 

planned
planned
March 30 2026: Construction Begins

Contractors will install sidewalk on the north side of the Fulton street from Plymouth to Worcester. 

 

planned
planned
June 2026: Construction ends

Construction is expected to end in June 2026.