Comprehensive Transportation Plan

Comprehensive Transportation Plan

The Comprehensive Transportation Plan Long range, needs-based plan; representing consensus by the community and the State on the future transportation system (including the existing system and improvements) needed to support anticipated growth and development over approximately a 25–30-year timeframe.

Comprehensive Transportation Plans are required by North Carolina Legislature (NC General Statute 136-66.2) and are jointly adopted by the North Carolina Department of Transportation and the Triangle West Transportation Planning Organization. Additionally, the Comprehensive Transportation Plan

  • is multimodal and includes highways, public transit, rail, bicycle, and pedestrian infrastructure
  • identifies all known transportation needs and is not fiscally constrained
  • does not include final design but informs final designs in short term planning efforts like the STIP

This project is designed as a central outreach and engagement hub for the Comprehensive Transportation Plan and amendments. 

Logo for Triangle Bikeway CTP Amendment

Triangle Bikeway CTP Amendment

The Triangle West Transportation Planning Organization (Triangle West TPO) proposes to amend the Comprehensive Transportation Plan (CTP) to add the Triangle Bikeway alignment and replace or modify several...

Project Timeline

complete
complete

Durham-Chapel Hill-Carrboro Metropolitan Transportation Plan Adopted in 2017

The Triangle West TPO Board and North Carolina Board of Transportation adopted the Triangle West TPO Comprehensive Transportation Plan (CTP) on May 10, 2017 and August 3, 2017, respectively.

 

The full report is in the document library on this page. The Comprehensive Transportation Plan can also be explored through our interactive CTP Map. 

complete
complete

Briggs Avenue Extension

Deleted the Briggs Ave Extension from CTP due to high costs with little benefits and the potential for heavy trucks to use residential streets.

 

Briggs Avenue Extension (Amendment 2) Final Report

complete
complete

Farrington Road

Changed a segment of Farrington Rd from a four-lane, divided highway to a two-lane, divided highway with bike lanes and crosswalks.

 

Farrington Road (Amendment 1) Final Report

complete
complete

Amendment 4

  • Removed the Durham-Orange Light Rail Transit alignment from CTP
  • Deleted and modified various roadway segments
  • Identified four Transit Emphasis Corridors (TECs)
  • Incorporated NCDOT’s updated Complete Streets Policy

Amendment 4 Final Report

complete
complete

Massey Chapel Road

Removed the realignment of Massey Chapel Road to maintain the existing alignment.

 

Massey Chapel Road Final Report

live
live

Triangle Bikeway West

The Triangle Bikeway West CTP Amendment proposed to include the Triangle Bikeway as a multi-use path and remove multi-use paths and bicycle lane projects that are adopted within the 2017 Comprehensive Transportation Plan and replace it with a single contigous project. 