Mallard Creek - David Taylor Drive

Mallard Creek - David Taylor Drive

Charlotte-Mecklenburg Storm Water Services will restore 5,875 Linear Feet of the Mallard Creek corridor from Mallard Creek Road to David Taylor Drive. The project will include stream restoration that would improve water quality and habitat and stabilize the stream banks for ecological and water quality uplift. There will be additional projects following the restoration managed by Mecklenburg County Park and Recreation and Charlotte Water.

Mecklenburg County Park and Recreation is planning to enhance the existing greenway trail between David Taylor Drive and Mallard Creek Road. The project will include paving of gravel trail, new connections, a trailhead parking lot and restrooms. The current schedule for the project is sometime after 2030 and is dependent on Charlotte Water’s construction schedule for the sewer main replacement in this area.
 
The Mallard Interceptor Project is a major wastewater improvement project designed to increase sewer capacity, reduce the amount of rainwater and groundwater entering the sewer system, and help prevent sewer overflows as the area continues to grow. Construction is currently expected to begin in Fall 2029 and be completed in Spring 2031.
 
The project will install approximately 3 miles of new 60-inch sewer pipe, beginning near the intersection of Toby Creek and North Tryon Street and continuing along Mallard Creek ending at Mallard Creek Road. The larger sewer line will provide additional capacity for future growth and improve the reliability of the wastewater system.

Timeline

Project Timeline

complete
complete

Planning

Completed in fall 2023

complete
complete

Design

Completed in spring 2026

live
live

Permitting

In progress

complete
complete

Property Easement Acquisition

Completed in fall 2025

planned
planned

Bid

Expected to begin in fall 2026

planned
planned

Construction

Expected to begin in spring 2027

planned
planned

Warranty

Expected to begin in spring 2028